# 772101484196
Unscheduled inspection
Start date: 2021-12-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101457600
Unscheduled inspection
Start date: 2021-12-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101347838
Unscheduled inspection
Start date: 2021-11-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100566738
Unscheduled inspection
Start date: 2021-09-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100518416
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration: 5
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: Assessment of the compliance of the performed works with the requirements of the project documentation
# 502004401148
Unscheduled inspection
Start date: 2020-05-21, end date: 2020-06-18, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: Supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms
# 502004302145
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-30, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: Supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms
# 502004235307
Unscheduled inspection
Start date: 2020-01-29, end date: 2020-02-04, duration: 5
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: Verification of the execution of the order dated 28102019 0536057800503 with a deadline of 28012020 Assessment of the compliance of the work performed with the requirements of the design documentation at the capital construction facility Outpatient clinic Zelenogradsky of the structural subdivision of MBUZ Polyclinic Lesnoy at the address Pushkinsky district, Zelenograd district, 141253 Shosseinaya Street, Russian Federation
# 501904215850
Unscheduled inspection
Start date: 2019-12-23, end date: 2020-01-27, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: protection of the rights and interests of employees and employers in accordance with the consideration of the application supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms and compliance with mandatory requirements and or requirements established by municipal legal acts
# 501904022410
Unscheduled inspection
Start date: 2019-11-05, end date: 2019-11-11, duration: 5
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: assessment of the compliance of the work performed with the requirements of technical regulations and design documentation at the capital construction facility of the Zelenogradsky Outpatient Clinic of the structural subdivision of the MBUZ "Polyclinic of Lesnoy" at the address of the Russian Federation, Pushkinsky district, Zelenograd district, 141253 Shosseynaya St.
# 501902785582
Unscheduled inspection
Start date: 2019-05-17, end date: 2019-06-04, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: This audit is conducted in order to protect the rights and interests of employees and employers in accordance with the consideration of applications from the gr. The objectives of this audit are supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms.7 The subject of this audit is to note the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 77190803413881
Unscheduled inspection
Start date: 2019-05-21, end date: 2019-06-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803421876
Unscheduled inspection
Start date: 2019-05-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803401997
Unscheduled inspection
Start date: 2019-04-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803371573
Unscheduled inspection
Start date: 2019-03-18, end date: 2019-04-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer's task of verification, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check and verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 501902587277
Unscheduled inspection
Start date: 2019-02-18, end date: 2019-03-15, duration: —
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: This audit is conducted in order to protect the rights and interests of employees and employers in accordance with the consideration of appeals from Petrov SV SB PP the objectives of this audit are supervision and control over compliance with labor legislation and other regulatory legal acts containing labor law norms The subject of this audit is to note the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 77190803327801
Unscheduled inspection
Start date: 2019-02-15, end date: 2019-03-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803340252
Unscheduled inspection
Start date: 2019-02-19, end date: 2019-02-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 771902484671
Unscheduled inspection
Start date: 2019-02-01, end date: 2019-02-28, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: The validation is conducted with the aim of protecting the rights and interests of RABOTNIKOV connection with the admission to the State labour Inspectorate in the city of Moscow from Oudomtrorle notice 190015 from 11012019 about the accident kucharovice 10012019 for agriculturally Alekseeva д12А Objectives of the examination are supervision and control over compliance with legislation and other normative legal acts containing norms of labor law the Subject of this review is compliance with mandatory requirements and / or requirements of the municipal legal acts according to the information contained in the notice of initiation of certain types of entrepreneurial activities with the mandatory requirements of conformity of the information contained in the statement and the documents of the legal entity or the individual entrepreneur on the legal status of a special license permit authorization coordination mandatory requirements as well as data about the specified legal entities and individual entrepreneurs contained in the unified state register of individual entrepreneurs and other Federal information resources the provisions of state control of the oversight bodies, municipal control activities for the prevention of harm to life, health of citizens harm to animals, plants, the environment, the cultural heritage monuments of history and culture of the peoples of the Russian Federation Museum objects and Museum collections included in the Museum Fund of the Russian Federation, documents of special historic importance to the scientific and cultural value are part of the national library of the Fund for the prevention of emergency situations of natural and technogenic character in the security of the state on elimination of consequences of the infliction of such harm
# 77190803320184
Unscheduled inspection
Start date: 2019-01-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803290258
Unscheduled inspection
Start date: 2018-12-04, end date: 2018-12-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803309828
Unscheduled inspection
Start date: 2018-12-29, end date: 2019-02-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803295918
Unscheduled inspection
Start date: 2018-12-10, end date: 2018-12-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803269312
Unscheduled inspection
Start date: 2018-11-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 501802153817
Unscheduled inspection
Start date: 2018-11-09, end date: 2018-11-13, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: inspections of the elimination of violations notification of the elimination of violations dated 29102018 P001945134014917839746 within the framework of the instruction 0346079800506 dated 04102018 with a period of elimination until 30102018 assessment of the compliance of the work performed with the requirements of technical regulations and design documentation at the capital construction facility Residential complex K1 Second stage of construction at the address Moscow region Khimki mkrLevoberezhny Ulsovkhoznaya building 13 compliance with mandatory requirements established by law
# 77180803277627
Unscheduled inspection
Start date: 2018-11-19, end date: 2018-12-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 501802021988
Unscheduled inspection
Start date: 2018-10-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 501802021945
Unscheduled inspection
Start date: 2018-10-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803247034
Unscheduled inspection
Start date: 2018-10-08, end date: 2018-10-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803246323
Unscheduled inspection
Start date: 2018-10-12, end date: 2018-10-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803253090
Unscheduled inspection
Start date: 2018-10-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803252939
Unscheduled inspection
Start date: 2018-10-16, end date: 2018-10-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803255237
Unscheduled inspection
Start date: 2018-10-19, end date: 2018-11-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803228084
Unscheduled inspection
Start date: 2018-09-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803228008
Unscheduled inspection
Start date: 2018-09-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803230487
Unscheduled inspection
Start date: 2018-09-18, end date: 2018-09-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 501801944186
Unscheduled inspection
Start date: 2018-09-25, end date: 2018-09-28, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0346079800505 dated 24082018 for elimination until 12092018 notification of elimination dated 07092018 P001179027101215975925 assessment of compliance of work performed with the requirements of technical regulations and design documentation at the capital construction facility Residential complex K1 The second stage of construction at the address Moscow region Khimki district Levoberezhny Ulsovkhoznaya building 13 verification of compliance with regulation 0346079800505 dated 24082018 for elimination until 12092018
# 501801903899
Unscheduled inspection
Start date: 2018-09-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 501800742075
Unscheduled inspection
Start date: 2018-08-10, end date: 2018-08-24, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0346078600508 dated 22062018 notice of elimination of violations P001159441485914845576 dated 31072018 assessment of compliance of work performed with the requirements of technical regulations and design documentation at the capital construction facility verification of compliance with regulation 0346078600508 dated 22062018
# 77180803213965
Unscheduled inspection
Start date: 2018-08-29, end date: 2018-09-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803198724
Unscheduled inspection
Start date: 2018-08-09, end date: 2018-08-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803208581
Unscheduled inspection
Start date: 2018-08-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 501800709972
Unscheduled inspection
Start date: 2018-07-17, end date: 2018-07-30, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0346079800504 dated 29062018 notice of elimination of violations P001810705200114277109 dated 06072018 assessment of compliance of work performed with the requirements of technical regulations and design documentation at the capital construction facility verification of compliance with regulation 0346079800504 dated 29062018
# 501800709909
Unscheduled inspection
Start date: 2018-07-17, end date: 2018-07-30, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0346079600505 dated 29062018 notification of elimination of violations P001063335505414277269 dated 06072018 assessment of compliance of work performed with the requirements of technical regulations and design documentation at the capital construction facility verification of compliance with regulation 0346079600505 dated 29062018
# 77180803189689
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803188813
Unscheduled inspection
Start date: 2018-07-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803175335
Unscheduled inspection
Start date: 2018-07-06, end date: 2018-07-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803173988
Unscheduled inspection
Start date: 2018-07-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803182411
Unscheduled inspection
Start date: 2018-07-20, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803184670
Unscheduled inspection
Start date: 2018-07-23, end date: 2018-07-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803175695
Unscheduled inspection
Start date: 2018-07-23, end date: 2018-08-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 501800509000
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-06, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0131147900502 dated 06062018
# 77180803163863
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803155081
Unscheduled inspection
Start date: 2018-06-11, end date: 2018-06-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803157808
Unscheduled inspection
Start date: 2018-06-05, end date: 2018-06-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803136283
Unscheduled inspection
Start date: 2018-06-06, end date: 2018-06-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803146831
Unscheduled inspection
Start date: 2018-06-04, end date: 2018-06-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 501800424377
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-05-22, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the elimination of violations notification of the elimination of violations P001526833695212751355 dated 03052018 0346079400503 dated 11042018 with a deadline of 22052017
# 501800424297
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-05-22, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the elimination of violations notification of the elimination of violations P001847357852612750981 dated 03052018 0346079300503 dated 11042018 with a deadline of 22052017
# 77180803129304
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-05-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803141237
Unscheduled inspection
Start date: 2018-05-18, end date: 2018-05-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 501800555327
Unscheduled inspection
Start date: 2018-05-30, end date: 2018-06-06, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0346079800503 of 20042018 notice of elimination of violations P001207317762712922056 of 11052018 assessment of compliance of work performed with the requirements of technical regulations and design documentation at the capital construction facility Residential complex K1 Second stage of construction at the address Moscow region Khimki mkrLevoberezhny Ulsovkhoznaya building 13 verification of compliance with regulation 0346079800503 of 20042018
# 501800555263
Unscheduled inspection
Start date: 2018-05-30, end date: 2018-06-06, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0346079600504 dated 13042018 notice of elimination of violations P001984215515812922351 dated 11052018 assessment of compliance of work performed with the requirements of technical regulations and design documentation at the capital construction facility Residential complex K7 with underground parking at Moscow region GKHIMKI mkrLevoberezhny Ulsovkhoznaya korp71 72 74 at Moscow region GKHIMKI mkrLevoberezhny Ulsovkhoznaya korp71 72 74 verification of compliance with regulation 0346079600504 from 13042018
# 501800555077
Unscheduled inspection
Start date: 2018-05-16, end date: 2018-05-18, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the elimination of violations notification of the elimination of violations R001806747903712753349 dated 03052018 0346078600507 dated 03042018 with a deadline of 21052018 assessment of the compliance of the work performed with the requirements of technical regulations and design documentation at the capital construction facility Residential complex with an integrated polyclinic for adults per 100 visits per shift and an integrated polyclinic for children per 100 visits per shift at the address Moscow region gHimki mkr678 kor8 verification of the fulfillment of the prescription 0346078600507 from 03042018 with a period of elimination until 21052018
# 77180803148798
Unscheduled inspection
Start date: 2018-05-25, end date: 2018-06-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803126124
Unscheduled inspection
Start date: 2018-04-19, end date: 2018-04-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 501800334633
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-20, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0346079800502 dated 02032018 notification of elimination of violations P001476886182511562800 dated 12032018 assessment of compliance of work performed with the requirements of technical regulations and design documentation at the capital construction facility verification of compliance with regulation 0346079800502 dated 02032018
# 77180803120291
Unscheduled inspection
Start date: 2018-04-09, end date: 2018-04-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803128792
Unscheduled inspection
Start date: 2018-04-24, end date: 2018-04-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803132164
Unscheduled inspection
Start date: 2018-04-26, end date: 2018-05-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803123279
Unscheduled inspection
Start date: 2018-04-26, end date: 2018-05-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803107001
Unscheduled inspection
Start date: 2018-03-30, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803091205
Unscheduled inspection
Start date: 2018-03-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803101482
Unscheduled inspection
Start date: 2018-03-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803102553
Unscheduled inspection
Start date: 2018-03-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803089855
Unscheduled inspection
Start date: 2018-03-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 501800334956
Unscheduled inspection
Start date: 2018-03-28, end date: 2018-04-02, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0346078600505 dated 22022018 notice of elimination of violations P001047003275811711457 dated 19032018 assessment of compliance of work performed with the requirements of technical regulations and design documentation at the capital construction facility verification of compliance with regulation 0346078600505 dated 22022018
# 501800334704
Unscheduled inspection
Start date: 2018-03-28, end date: 2018-03-30, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0346079600502 dated 22022018 notice of elimination of violations P001557713801111715255 dated 19032018 assessment of compliance of work performed with the requirements of technical regulations and design documentation at the capital construction facility verification of compliance with regulation 0346079600502 dated 22022018
# 77180803079235
Unscheduled inspection
Start date: 2018-02-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803091383
Unscheduled inspection
Start date: 2018-02-28, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803091232
Unscheduled inspection
Start date: 2018-02-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803072770
Unscheduled inspection
Start date: 2018-01-30, end date: 2018-02-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803079533
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803066171
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-01-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803055618
Unscheduled inspection
Start date: 2018-01-22, end date: 2018-02-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802884870
Unscheduled inspection
Start date: 2017-12-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 50170803032940
Unscheduled inspection
Start date: 2017-12-26, end date: 2018-01-30, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the execution of the order assessment of the compliance of the work performed with the requirements of technical regulations and project documentation verification of the execution of the order
# 77170803012675
Unscheduled inspection
Start date: 2017-12-21, end date: 2017-12-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170802994509
Unscheduled inspection
Start date: 2017-12-18, end date: 2017-12-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 50170803029494
Unscheduled inspection
Start date: 2017-12-19, end date: 2017-12-21, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the elimination of violations notification of the elimination of violations P00196707680039821814 dated 11122017 within the framework of the instruction 0908000400504 dated 15112017 with a deadline of 15122017 assessment of the compliance of the work performed with the requirements of technical regulations and design documentation at the capital construction facility "DIY Center building, the first stage of construction of the administrative and trading complex RetailPark Zheleznodorozhny" at the address Moscow region Balashikha, Zheleznodorozhny Prigorodnaya MKR near house 119
# 77170803008007
Unscheduled inspection
Start date: 2017-12-15, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 50170802867094
Unscheduled inspection
Start date: 2017-11-08, end date: 2017-11-14, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: inspections of the elimination of violations notification of the elimination of violations P00134368404509123969 dated 31102017 within the framework of the instruction 0908000400502 dated 03102017 with a deadline of 01112017 assessment of the compliance of the work performed with the requirements of technical regulations and design documentation at the capital construction facility "DIY Center building, the first stage of construction of the administrative and trading complex RetailPark Zheleznodorozhny" at the address Moscow region Balashikha, Zheleznodorozhny Prigorodnaya MKR near house 119
# 50170802821496
Unscheduled inspection
Start date: 2017-11-08, end date: 2017-11-14, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the elimination of violations notification of the elimination of violations P00100758395569109916 dated 31.102017 within the framework of regulation 0346079300502 dated 03.102017 with a deadline of 221117
# 50170802821417
Unscheduled inspection
Start date: 2017-11-08, end date: 2017-11-14, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the elimination of violations notification of the elimination of violations P00100758395569109916 dated 31.102017 within the framework of regulation 0346079300502 dated 03.102017 with a deadline of 221117
# 50170802887893
Unscheduled inspection
Start date: 2017-11-22, end date: 2017-11-23, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of the execution of the order from 10102017 0908065700509 with a deadline of up to 2112017 assessment of the compliance of the work performed with the requirements of technical regulations and design documentation at the capital construction facility Multi-storey residential building with built-in premises building 29 at 143900 Balashikha, Moscow region, near the village of Pavlino
# 77170802889115
Unscheduled inspection
Start date: 2017-11-23, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 50170802888756
Unscheduled inspection
Start date: 2017-11-20, end date: 2017-11-24, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: verification of compliance with regulation 0346078600503 dated 2010-2017 for elimination until 06112017 notification of elimination of violations P00164406543299124269 dated 31102017 assessment of compliance of work performed with the requirements of technical regulations and design documentation at the capital construction facility verification of compliance with regulation 0346078600503 dated 2010-2017 for elimination until 06112017
# 77170802861124
Unscheduled inspection
Start date: 2017-11-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170802861309
Unscheduled inspection
Start date: 2017-11-14, end date: 2017-11-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802470406
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-11-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor