Found 6 inspections:

# 00170802958195
Unscheduled inspection
Start date: 2017-12-06, end date: 2017-12-12, duration:
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the implementation of paragraphs 15 of the previously issued regulation dated 14082017 431810101123the objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulation federal State energy supervision in the field of heat supply


# 00170802751670
Unscheduled inspection
Start date: 2017-10-16, end date: —, duration:
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 00170802958195
Unscheduled inspection
Start date: 2017-12-06, end date: 2017-12-12, duration:
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the implementation of paragraphs 15 of the previously issued regulation dated 14082017 431810101123the objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulation federal State energy supervision in the field of heat supply


# 00170802751670
Unscheduled inspection
Start date: 2017-10-16, end date: 2017-10-18, duration:
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the implementation of paragraphs 110 of the previously issued regulation dated 25082017 431810282499101139the objectives of this audit are to monitor the measures taken by a legal entity to comply with the regulation Federal State Energy Supervision


# 00170801924737
Unscheduled inspection
Start date: 2017-08-22, end date: 2017-08-25, duration:
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated July 10, 2017 256 "On monitoring the progress of preparation of electric power and heat supply facilities for operation in the autumn-winter period 2017-2018" issued on the basis of the instruction of the Deputy Chairman of the Government of the Russian Federation dated July 29, 2017 DKP94194


# 16170701524843
Unscheduled inspection
Start date: 2017-04-10, end date: 2017-04-21, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Respublike Tatarstan
Purpose of inspection: control of the previously issued regulation No. 59159 dated May 24, 2016 on the elimination of violations of fire safety requirements on the implementation of measures to ensure fire safety at protection facilities and to prevent the threat of fire