# 52170701734526
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-06-27, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out on the basis of the approved inspection program for the capital construction facility and also in order to verify compliance with the requirements of the regulation dated 26042017 5190303020415 issued to the contractor Tornado LLC to assess the compliance of work and construction materials used in the construction process with the requirements of technical regulations norms and rules and design documentation, including during the construction stages, the device of structures and the roof of the attic floors installation of stairs L1 L2 L3 L4 internal walls and partitions Inspection task monitoring compliance with the requirements of urban planning legislation and other regulatory legal acts in the field of construction and other safety