Found 65 inspections:

# 772004199806
Unscheduled inspection
Start date: 2020-01-16, end date: 2020-02-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used


# 772004199770
Unscheduled inspection
Start date: 2020-01-16, end date: 2020-02-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used


# 772004199176
Unscheduled inspection
Start date: 2020-01-16, end date: 2020-02-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used


# 772004200090
Unscheduled inspection
Start date: 2020-01-17, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772004199112
Unscheduled inspection
Start date: 2020-01-17, end date: 2020-02-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Celi proverkiprovedenie meropriyatii po kontrolyu v svyazi s postupleniem izvescheniya zastroischika zakazchikaZadachi proverkipreduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii trebovanii proektnoi dokumentacii zakonodatelstva o gradostroitelnoi deyatelnostiPredmet proverkisootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovproverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom


# 772004199143
Unscheduled inspection
Start date: 2020-01-17, end date: 2020-02-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Celi proverkiprovedenie meropriyatii po kontrolyu v svyazi s postupleniem izvescheniya zastroischika zakazchikaZadachi proverkipreduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii trebovanii proektnoi dokumentacii zakonodatelstva o gradostroitelnoi deyatelnostiPredmet proverkisootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovproverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom


# 771904056758
Unscheduled inspection
Start date: 2019-12-04, end date: 2019-12-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used


# 771904056639
Unscheduled inspection
Start date: 2019-12-04, end date: 2019-12-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used


# 771904051886
Unscheduled inspection
Start date: 2019-12-04, end date: 2019-12-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Celi proverkiprovedenie meropriyatii po kontrolyu v svyazi s postupleniem izvescheniya zastroischika zakazchikaZadachi proverkipreduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii trebovanii proektnoi dokumentacii zakonodatelstva o gradostroitelnoi deyatelnostiPredmet proverkisootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovproverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom


# 771904037154
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used


# 771904037189
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used


# 771904056689
Unscheduled inspection
Start date: 2019-12-05, end date: 2019-12-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer to the customer, the tasks of the audit are to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements capital construction facility with metering devices for energy resources used


# 771903998978
Unscheduled inspection
Start date: 2019-11-22, end date: 2019-12-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used


# 771903994763
Unscheduled inspection
Start date: 2019-11-22, end date: —, duration:
Authority:
Purpose of inspection:


# 771903994760
Unscheduled inspection
Start date: 2019-11-26, end date: 2019-12-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903937865
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-11-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903937320
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-11-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903937376
Unscheduled inspection
Start date: 2019-11-07, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 771903827099
Unscheduled inspection
Start date: 2019-10-10, end date: 2019-10-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903639402
Unscheduled inspection
Start date: 2019-09-16, end date: —, duration:
Authority:
Purpose of inspection:


# 771903775266
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-22, duration: 20
Authority: Komitet goroda Moskvy po obespecheniyu realizacii investicionnyh proektov v stroitelstve i kontrolyu v oblasti dolevogo stroitelstva
Purpose of inspection: To establish that the purpose and objective of this audit is to verify compliance with the mandatory requirements of legislation on participation in the shared construction of apartment buildings and or other real estate objects. The subject of an unscheduled documentary audit is compliance with the requirements of legislation on participation in the shared construction of apartment buildings and or other real estate objects


# 771903643100
Unscheduled inspection
Start date: 2019-09-25, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803490280
Unscheduled inspection
Start date: 2019-09-03, end date: 2019-09-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803490278
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 771903639322
Unscheduled inspection
Start date: 2019-09-06, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803477003
Unscheduled inspection
Start date: 2019-08-15, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803472536
Unscheduled inspection
Start date: 2019-08-08, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803485402
Unscheduled inspection
Start date: 2019-08-28, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803462185
Unscheduled inspection
Start date: 2019-07-23, end date: 2019-08-07, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803462184
Unscheduled inspection
Start date: 2019-07-23, end date: 2019-08-07, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803415123
Unscheduled inspection
Start date: 2019-05-16, end date: 2019-05-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803402710
Unscheduled inspection
Start date: 2019-04-24, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803402707
Unscheduled inspection
Start date: 2019-04-24, end date: 2019-05-06, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: provedenie meropriyatii po kontrolyu v svyazi s proverkoi vypolneniya predpisaniyapreduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii trebovanii proektnoi dokumentacii zakonodatelstva o gradostroitelnoi deyatelnostiproverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom


# 77190803323199
Unscheduled inspection
Start date: 2019-02-01, end date: 2019-02-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803321739
Unscheduled inspection
Start date: 2019-01-30, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803313913
Unscheduled inspection
Start date: 2019-01-16, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803306421
Unscheduled inspection
Start date: 2018-12-26, end date: 2019-01-11, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803306419
Unscheduled inspection
Start date: 2018-12-26, end date: 2019-01-11, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803280219
Unscheduled inspection
Start date: 2018-11-21, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803276458
Unscheduled inspection
Start date: 2018-11-21, end date: 2018-12-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor, compliance of the work and construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803267539
Unscheduled inspection
Start date: 2018-11-07, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803267538
Unscheduled inspection
Start date: 2018-11-07, end date: 2018-11-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803276454
Unscheduled inspection
Start date: 2018-11-16, end date: 2018-12-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803241050
Unscheduled inspection
Start date: 2018-10-03, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803248456
Unscheduled inspection
Start date: 2018-10-09, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803250353
Unscheduled inspection
Start date: 2018-10-15, end date: 2018-10-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803250348
Unscheduled inspection
Start date: 2018-10-15, end date: 2018-11-06, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803226107
Unscheduled inspection
Start date: 2018-09-18, end date: 2018-10-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803226009
Unscheduled inspection
Start date: 2018-09-18, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77180803229297
Unscheduled inspection
Start date: 2018-09-19, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803221091
Unscheduled inspection
Start date: 2018-09-10, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803222668
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-09-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803198876
Unscheduled inspection
Start date: 2018-08-10, end date: 2018-08-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803194656
Unscheduled inspection
Start date: 2018-08-07, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803194670
Unscheduled inspection
Start date: 2018-08-07, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803206250
Unscheduled inspection
Start date: 2018-08-22, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803180264
Unscheduled inspection
Start date: 2018-07-11, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803172061
Unscheduled inspection
Start date: 2018-07-04, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803185680
Unscheduled inspection
Start date: 2018-07-25, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803163672
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803168515
Unscheduled inspection
Start date: 2018-06-27, end date: 2018-07-02, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803164484
Unscheduled inspection
Start date: 2018-06-20, end date: 2018-06-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803163698
Unscheduled inspection
Start date: 2018-06-20, end date: 2018-07-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803147408
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-06-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, certificates of admission issued by a self-regulatory organization to works that affect the safety of capital construction facilities


# 77180803147448
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-06-06, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, certificates of admission issued by a self-regulatory organization to works that affect the safety of capital construction facilities


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.