Found 9 inspections:

# 302101532912
Unscheduled inspection
Start date: 2021-12-27, end date: —, duration:
Authority:
Purpose of inspection:


# 302101210569
Unscheduled inspection
Start date: 2021-09-08, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: NOTICE OF COMPLETION OF THE CONSTRUCTION OF the ACS – Kindergarten for 330 places in the Trusovsky district of Astrakhan, the residential district "Zapadny-2


# 302101207800
Unscheduled inspection
Start date: 2021-08-10, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: NOTICE OF COMPLETION OF THE CONSTRUCTION OF the ACS – Construction of a school for 1000 students on 3rd Zelenginskaya St., Nikitinsky Bugor-2 microdistrict in the Kirovsky district of Astrakhan (1st stage)


# 302004445019
Unscheduled inspection
Start date: 2020-04-09, end date: —, duration:
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection:


# 302004297867
Unscheduled inspection
Start date: 2020-01-19, end date: 2020-01-26, duration:
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: notice of the start of construction of the construction of a block modular boiler house on 2nd proezd Mostostroiteley street in the Trusovsky district of Astrakhan


# 301902852949
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-28, duration:
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: ACS Construction of a 330-seat residential complex in the Trusovsky district of Astrakhan


# 301802463226
Unscheduled inspection
Start date: 2018-12-20, end date: 2018-12-28, duration:
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: OKS Kindergarten in the Babaevsky microdistrict in the Leninsky district of Astrakhan


# 30160700992584
Unscheduled inspection
Start date: 2016-10-06, end date: 2016-11-02, duration:
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: The purpose of the announcement of the completion of construction is the construction of an access highway from the Astrakhan Kambyak highway to the Ivanmakar hill in the village of Karagali in the Privolzhsky district of the Astrakhan regioncorrection


# 30160700882345
Unscheduled inspection
Start date: 2016-09-26, end date: 2016-10-21, duration:
Authority: Sluzhba stroitelnogo nadzora Astrahanskoi oblasti
Purpose of inspection: This inspection is carried out for the purpose of notifying the completion of the construction of a capital construction facility Reconstruction of a pumping station at the source of the Kutum river in Astrakhan. The objectives of this inspection are to verify the compliance of completed works with design documentation, building regulations, rules and technical regulations during the construction of a capital construction facility Reconstruction of a pumping station at the source of the Kutum river in Astrakhan


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.