# 001903053257
Unscheduled inspection
Start date: 2019-08-28, end date: 2019-09-24, duration: —
Authority: SeveroVostochnoe territorialnoe upravlenie Federalnogo agentstva po rybolovstvu
Purpose of inspection: Purpose analysis evaluation of the information contained in the letter of the acting head of the Kamchatka branch of the Federal State Budgetary Institution VNIRO KamchatNIRO MN Kovalenko on violation of environmental legislation Tasks determination of compliance of economic activities with the provisions of legislative and other regulatory legal acts of the Russian Federation in the field of protection of aquatic biological resources and their habitat within the authority of the Department definition of measures aimed at eliminating offenses subject to compliance with mandatory requirements of the environmental legislation of the Russian Federation carrying out measures to prevent harm to aquatic biological resources and their habitat
# 001902471347
Unscheduled inspection
Start date: 2019-01-11, end date: 2019-01-24, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used
# 001802093916
Unscheduled inspection
Start date: 2018-11-06, end date: 2018-11-19, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used 2 Checking the availability of a construction permit 3 Checking compliance with the requirements established by parts 2 3 and 3_1 of Article 52
# 001802093911
Unscheduled inspection
Start date: 2018-11-06, end date: 2018-11-19, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used 2 Checking the availability of a construction permit 3 Checking compliance with the requirements established by parts 2 3 and 3_1 of Article 52
# 001800592601
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-21, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of the inspection program, which should be notified in accordance with the established procedure to the head of the Closed Joint Stock Company "Disturbing Glow" within 24 hours before the start of the inspection
# 001800592593
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-21, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of the inspection program, which should be notified in accordance with the established procedure to the head of the Closed Joint Stock Company "Disturbing Glow" within 24 hours before the start of the inspection
# 001800190593
Unscheduled inspection
Start date: 2018-03-07, end date: 2018-04-05, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of CJSC "Alarming Glow" prescriptions PR7534202K06 dated 25122017 of the Far Eastern Department of Rostechnadzor the deadline for the execution of n 1 2 3 expired 15022018, which should be notified to CJSC "Alarming Glow" in any available way, at least 24 hours in advance, prevention, detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation in the field of industrial safety mandatory compliance with the requirements of the state control bodies supervision of municipal control bodies
# 00170803045777
Unscheduled inspection
Start date: 2017-12-27, end date: —, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170802965179
Unscheduled inspection
Start date: 2017-12-27, end date: 2018-01-31, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 5_1 of Article 6 of the Urban Planning Code of the Russian Federation
# 00170802965176
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-12-18, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 5_1 of Article 6 of the Urban Planning Code of the Russian Federation
# 00170802965175
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-12-18, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 5_1 of Article 6 of the Urban Planning Code of the Russian Federation
# 00170802761429
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-12-18, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of a notice of completion of construction and compliance of completed works and applied building materials during the construction of reconstruction of a capital construction facility as well as the results of such work with the requirements of technical regulations design documentation including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 00170802761427
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-12-18, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of a notice of completion of construction and compliance of completed works and applied building materials during the construction of reconstruction of a capital construction facility as well as the results of such work with the requirements of technical regulations design documentation including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 00170701818499
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-08-04, duration: —
Authority: SeveroVostochnoe territorialnoe upravlenie Federalnogo agentstva po rybolovstvu
Purpose of inspection: Study analysis evaluation of information from circulation Determination of compliance of the performed business activities with mandatory requirements Identification and implementation of measures aimed at eliminating offenses
# 00160701073404
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-11-03, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out for the purpose of monitoring the execution of JSC "Disturbing Glow" of the prescription PR7525002K06 from 30092016 of the Far Eastern Department of Rostechnadzor the deadline for the execution of p15 expired on 17102016 The tasks of this inspection are to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation in the field of industrial safety mandatory requirements The subject of this inspection is the fulfillment of the instructions of state control bodies supervision of municipal control bodies
# 412100217460
Unscheduled inspection
Start date: 2021-05-19, end date: —, duration: 5
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Control over the execution by a legal entity or an individual entrepreneur of a previously issued order to eliminate an identified violation of mandatory labor requirements, the deadline for which has expired, Order No.41/6-1-21- UV/12-372-I/165 dated 02/08/2021
# 412100181023
Unscheduled inspection
Start date: 2021-05-04, end date: —, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing norms of labor law, protection of the rights and interests of employees (
# 412100164143
Unscheduled inspection
Start date: 2021-04-26, end date: 2021-04-30, duration: 5
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing norms of labor law, protection of the rights and interests of employees
# 252100157056
Unscheduled inspection
Start date: 2021-04-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 412105330645
Unscheduled inspection
Start date: 2021-02-02, end date: 2021-02-08, duration: 5
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing norms of labor law, protection of the rights and interests of employees
# 412004408897
Unscheduled inspection
Start date: 2020-05-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 412004311204
Unscheduled inspection
Start date: 2020-03-06, end date: 2020-03-13, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms protecting the rights and interests of employees
# 412004330706
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-25, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Kamchatskomu krayu
Purpose of inspection: Verification of the execution of JSC "Disturbing Glow" of the previously issued order on the elimination of violations of legislation in the field of environmental protection and violations of environmental requirements dated February 12, 2019 34391901
# 412004262107
Unscheduled inspection
Start date: 2020-02-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 412004174906
Unscheduled inspection
Start date: 2020-01-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 411904092075
Unscheduled inspection
Start date: 2019-12-27, end date: 2020-01-10, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms protecting the rights and interests of employees
# 411904072150
Unscheduled inspection
Start date: 2019-12-17, end date: 2019-12-23, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms 10001244260
# 411904001306
Unscheduled inspection
Start date: 2019-11-28, end date: 2019-12-04, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms protecting the rights and interests of employees
# 411903939179
Unscheduled inspection
Start date: 2019-11-28, end date: 2019-12-04, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms protecting the rights and interests of employees
# 411903939217
Unscheduled inspection
Start date: 2019-11-28, end date: 2019-12-04, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms protecting the rights and interests of employees
# 411903871075
Unscheduled inspection
Start date: 2019-10-21, end date: 2019-11-18, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms protecting the rights and interests of employees
# 411903782927
Unscheduled inspection
Start date: 2019-10-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 411902927773
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kamchatskogo kraya
Purpose of inspection: It is carried out in order to assess the compliance of the capital construction facility and related construction processes with safety requirements
# 001903053257
Unscheduled inspection
Start date: 2019-08-28, end date: 2019-09-24, duration: —
Authority: SeveroVostochnoe territorialnoe upravlenie Federalnogo agentstva po rybolovstvu
Purpose of inspection: Purpose analysis evaluation of the information contained in the letter of the acting head of the Kamchatka branch of the Federal State Budgetary Institution VNIRO KamchatNIRO MN Kovalenko on violation of environmental legislation Tasks determination of compliance of economic activities with the provisions of legislative and other regulatory legal acts of the Russian Federation in the field of protection of aquatic biological resources and their habitat within the authority of the Department definition of measures aimed at eliminating offenses subject to compliance with mandatory requirements of the environmental legislation of the Russian Federation carrying out measures to prevent harm to aquatic biological resources and their habitat
# 411902896069
Unscheduled inspection
Start date: 2019-07-19, end date: 2019-08-15, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other normative legal acts containing norms of labor law protection of the rights and interests of employees supervision and control over compliance with labor legislation and other normative legal acts containing norms of labor law compliance with mandatory requirements and or requirements established by municipal legal acts
# 411902771791
Unscheduled inspection
Start date: 2019-06-04, end date: 2019-07-02, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Purpose Task Subject
# 411905141295
Unscheduled inspection
Start date: 2019-05-06, end date: 2019-05-08, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kamchatskogo kraya
Purpose of inspection: The purpose is to assess the compliance of the capital construction facility and related construction and reconstruction processes with safety requirements Tasks prevention detection and suppression of violations of the legislation of the Russian Federation on urban development activities including technical regulations norms and rules and design documentation during the construction reconstruction of the capital construction facility The subject of verification
# 411905147267
Unscheduled inspection
Start date: 2019-05-06, end date: 2019-05-08, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kamchatskogo kraya
Purpose of inspection: The purpose is to assess the compliance of the capital construction facility and related construction and reconstruction processes with safety requirements Tasks prevention detection and suppression of violations of the legislation of the Russian Federation on urban development activities including technical regulations norms and rules and design documentation during the construction reconstruction of the capital construction facility The subject of verification
# 411905145762
Unscheduled inspection
Start date: 2019-05-06, end date: 2019-05-08, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kamchatskogo kraya
Purpose of inspection: The purpose is to assess the compliance of the capital construction facility and related construction and reconstruction processes with safety requirements Tasks prevention detection and suppression of violations of the legislation of the Russian Federation on urban development activities including technical regulations norms and rules and design documentation during the construction reconstruction of the capital construction facility The subject of verification
# 411905145684
Unscheduled inspection
Start date: 2019-05-06, end date: 2019-05-08, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kamchatskogo kraya
Purpose of inspection: The purpose is to assess the compliance of the capital construction facility and related construction and reconstruction processes with safety requirements Tasks prevention detection and suppression of violations of the legislation of the Russian Federation on urban development activities including technical regulations norms and rules and design documentation during the construction reconstruction of the capital construction facility The subject of verification
# 411902687496
Unscheduled inspection
Start date: 2019-05-06, end date: 2019-05-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Kamchatskogo kraya
Purpose of inspection: the purpose is to assess the compliance of the capital construction facility and related construction processes with safety requirements the task is to prevent identify and suppress violations of the legislation of the Russian Federation on urban development activities including technical regulations other regulatory legal acts and project documentation during the construction of the facility the subject is compliance with the legislation of the Russian Federation on urban development activities compliance of the work performed applied building materials and the results of such work with the requirements design documentation for the construction of the facility
# 411902507634
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-22, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with the established procedure for the investigation and accounting of accidents at work in connection with the received request of an employee vh 41728219iz from 06022019
# 411902546884
Unscheduled inspection
Start date: 2019-02-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001902471347
Unscheduled inspection
Start date: 2019-01-11, end date: 2019-01-24, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used
# 411902527630
Unscheduled inspection
Start date: 2019-01-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 411802331262
Unscheduled inspection
Start date: 2018-12-20, end date: 2019-01-24, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: The purpose of the federal state supervision of compliance with labor legislation and other normative legal acts containing norms of labor law protection of the rights and interests of employees in connection with the consideration of the appeal dated 17122018 417279318ob Task supervision and control of compliance with labor legislation and other normative legal acts containing norms of labor law Subject compliance by the employer in the course of its activities with the requirements of labor legislation and other normative legal acts containing norms of labor law
# 001802393904
Unscheduled inspection
Start date: 2018-12-06, end date: 2018-12-26, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used
# 001802301602
Unscheduled inspection
Start date: 2018-12-07, end date: 2018-12-07, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control over the implementation of the previously issued instruction on the elimination of identified violations from 30112018 PR7522602K05, the deadline for which expired on 03122018
# 001802093916
Unscheduled inspection
Start date: 2018-11-06, end date: 2018-11-19, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used 2 Checking the availability of a construction permit 3 Checking compliance with the requirements established by parts 2 3 and 3_1 of Article 52
# 001802093911
Unscheduled inspection
Start date: 2018-11-06, end date: 2018-11-19, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of the work performed and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used 2 Checking the availability of a construction permit 3 Checking compliance with the requirements established by parts 2 3 and 3_1 of Article 52
# 411802115319
Unscheduled inspection
Start date: 2018-11-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 411801855739
Unscheduled inspection
Start date: 2018-10-03, end date: 2018-10-30, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms protecting the rights and interests of employees
# 411801997447
Unscheduled inspection
Start date: 2018-10-19, end date: 2018-11-16, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: compliance with tr leaven
# 411801997427
Unscheduled inspection
Start date: 2018-10-19, end date: 2018-11-16, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: compliance by the employer in the course of his activity with the requirements of labor legislation and other regulatory legal acts containing labor law norms
# 411801505065
Unscheduled inspection
Start date: 2018-09-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 411801540565
Unscheduled inspection
Start date: 2018-09-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001800592601
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-21, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of the inspection program, which should be notified in accordance with the established procedure to the head of the Closed Joint Stock Company "Disturbing Glow" within 24 hours before the start of the inspection
# 001800592593
Unscheduled inspection
Start date: 2018-09-03, end date: 2018-09-21, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of the inspection program, which should be notified in accordance with the established procedure to the head of the Closed Joint Stock Company "Disturbing Glow" within 24 hours before the start of the inspection
# 411800673715
Unscheduled inspection
Start date: 2018-08-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 411800673707
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-21, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: compliance with the labor law
# 411800540148
Unscheduled inspection
Start date: 2018-07-09, end date: 2018-07-09, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: Verification of the execution of a previously issued prescription
# 411800450859
Unscheduled inspection
Start date: 2018-06-13, end date: 2018-07-10, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Kamchatskomu krayu
Purpose of inspection: verification of the execution of the regulation dated 16062017 3436173
# 001800578659
Unscheduled inspection
Start date: 2018-06-27, end date: 2018-07-17, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of the inspection program, which should be notified in accordance with the established procedure to the head of the Closed Joint Stock Company "Disturbing Glow" within 24 hours before the start of the inspection
# 001800490453
Unscheduled inspection
Start date: 2018-06-27, end date: 2018-07-17, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of the inspection program, which should be notified in accordance with the established procedure to the head of the Closed Joint Stock Company "Disturbing Glow" within 24 hours before the start of the inspection
# 001800361804
Unscheduled inspection
Start date: 2018-04-18, end date: 2018-05-03, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 001800361800
Unscheduled inspection
Start date: 2018-04-18, end date: 2018-05-03, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 001800259873
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-27, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the technical customer hereinafter referred to as the contractor compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 001800259957
Unscheduled inspection
Start date: 2018-04-16, end date: 2018-04-27, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation prevention detection and suppression of violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the technical customer hereinafter referred to as the contractor compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 411800206880
Unscheduled inspection
Start date: 2018-03-05, end date: 2018-04-03, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Kamchatskomu krayu
Purpose of inspection: verification of the execution of the regulation dated 16062017 34491702
# 001800190593
Unscheduled inspection
Start date: 2018-03-07, end date: 2018-04-05, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the execution of CJSC "Alarming Glow" prescriptions PR7534202K06 dated 25122017 of the Far Eastern Department of Rostechnadzor the deadline for the execution of n 1 2 3 expired 15022018, which should be notified to CJSC "Alarming Glow" in any available way, at least 24 hours in advance, prevention, detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation in the field of industrial safety mandatory compliance with the requirements of the state control bodies supervision of municipal control bodies
# 411800090402
Unscheduled inspection
Start date: 2018-02-16, end date: 2018-03-20, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: compliance with labor laws
# 411800053013
Unscheduled inspection
Start date: 2018-02-05, end date: 2018-03-05, duration: —
Authority: Gosudarstvennaya inspekciya truda v Kamchatskom krae
Purpose of inspection: compliance with labor laws
# 00170803045777
Unscheduled inspection
Start date: 2017-12-27, end date: 2018-01-31, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban development activities, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the technical customer, hereinafter referred to as the contractor
# 00170802965179
Unscheduled inspection
Start date: 2017-12-27, end date: 2018-01-31, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 5_1 of Article 6 of the Urban Planning Code of the Russian Federation
# 00170803013081
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-12-18, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance of the performed works and applied building materials in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility
# 00170803013080
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-12-18, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance of the performed works and applied building materials in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility
# 00170802965176
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-12-18, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 5_1 of Article 6 of the Urban Planning Code of the Russian Federation
# 00170802965175
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-12-18, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 5_1 of Article 6 of the Urban Planning Code of the Russian Federation
# 41170802892363
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-11-27, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Kamchatskomu krayu
Purpose of inspection: verification of the execution of the regulation from 11082017 34391701
# 00170802761429
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-12-18, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of a notice of completion of construction and compliance of completed works and applied building materials during the construction of reconstruction of a capital construction facility as well as the results of such work with the requirements of technical regulations design documentation including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 00170802761427
Unscheduled inspection
Start date: 2017-11-21, end date: 2017-12-18, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Implementation of federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of a notice of completion of construction and compliance of completed works and applied building materials during the construction of reconstruction of a capital construction facility as well as the results of such work with the requirements of technical regulations design documentation including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 41170802740780
Unscheduled inspection
Start date: 2017-10-09, end date: 2017-10-18, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Kamchatskomu krayu
Purpose of inspection: in order to match the condition of premises buildings structures and other technical means equipment of other objects that are supposed to be used by the license applicant
# 41170802761496
Unscheduled inspection
Start date: 2017-10-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 41170802694014
Unscheduled inspection
Start date: 2017-09-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 41170701818492
Unscheduled inspection
Start date: 2017-07-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00170701818499
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-08-04, duration: —
Authority: SeveroVostochnoe territorialnoe upravlenie Federalnogo agentstva po rybolovstvu
Purpose of inspection: Study analysis evaluation of information from circulation Determination of compliance of the performed business activities with mandatory requirements Identification and implementation of measures aimed at eliminating offenses
# 41170701613246
Unscheduled inspection
Start date: 2017-05-10, end date: 2017-05-26, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Kamchatskomu krayu
Purpose of inspection: In order to assess the possibility of granting a license for the collection transportation use neutralization disposal of waste of hazard classes I0IV on the basis of an application for conformity assessment of the information contained in the submitted documents
# 41170701658549
Unscheduled inspection
Start date: 2017-05-29, end date: 2017-06-22, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Kamchatskomu krayu
Purpose of inspection: in order to match the condition of premises buildings structures and other technical means equipment of other objects that are supposed to be used by the license applicant
# 41170701637296
Unscheduled inspection
Start date: 2017-05-22, end date: 2017-06-19, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Kamchatskomu krayu
Purpose of inspection: verification of regulations dated 28102016 3436165 3436166 34491620 34491624
# 41170701548367
Unscheduled inspection
Start date: 2017-04-14, end date: 2017-05-16, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Kamchatskomu krayu
Purpose of inspection: Verification of the facts received in the letter of the Ministry of Natural Resources and Ecology of the Kamchatka Territory dated 05042017 26021295
# 41170701402872
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-03-22, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere prirodopolzovaniya po Kamchatskomu krayu
Purpose of inspection: verification of regulations 34491621 34491622 dated 28102016
# 41160700879202
Unscheduled inspection
Start date: 2016-12-19, end date: 2016-12-20, duration: —
Authority: Upravlenie gosavtodornadzora po Kamchatskomu krayu
Purpose of inspection: verification of the execution of regulation 56 of 26092016
# 00160701073404
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-11-03, duration: —
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out for the purpose of monitoring the execution of JSC "Disturbing Glow" of the prescription PR7525002K06 from 30092016 of the Far Eastern Department of Rostechnadzor the deadline for the execution of p15 expired on 17102016 The tasks of this inspection are to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation in the field of industrial safety mandatory requirements The subject of this inspection is the fulfillment of the instructions of state control bodies supervision of municipal control bodies
# 41160601699149
Unscheduled inspection
Start date: 2016-07-04, end date: 2016-07-20, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Kamchatskomu krayu
Purpose of inspection: control of the execution of the prescription
# 41160601604901
Unscheduled inspection
Start date: 2016-04-27, end date: 2016-04-27, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Kamchatskomu krayu
Purpose of inspection: control of the execution of the regulation of 22102015 331N
# 41150601375357
Unscheduled inspection
Start date: 2015-11-12, end date: 2015-11-27, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Kamchatskomu krayu
Purpose of inspection: control of the execution of the prescription
# 41150600497022
Unscheduled inspection
Start date: 2015-08-19, end date: 2015-08-28, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Kamchatskomu krayu
Purpose of inspection: control of the execution of the prescription