# 77180803220188
Unscheduled inspection
Start date: 2018-09-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803192463
Unscheduled inspection
Start date: 2018-08-03, end date: 2018-08-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803136963
Unscheduled inspection
Start date: 2018-05-08, end date: 2018-05-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803114062
Unscheduled inspection
Start date: 2018-03-30, end date: 2018-04-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803079659
Unscheduled inspection
Start date: 2018-01-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803070100
Unscheduled inspection
Start date: 2018-01-30, end date: 2018-02-27, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used