# 742101436263
Unscheduled inspection
Start date: 2021-12-15, end date: —, duration:
Authority:
Purpose of inspection:


# 742100554442
Unscheduled inspection
Start date: 2021-09-13, end date: 2021-09-17, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the installation of the grillage used 1-6 (in the process of work). and the construction materials used in the process of construction, reconstruction of the capital construction facility, as well as the results of such work to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping the capital construction facility with metering devices for energy resources used. 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 742100231936
Unscheduled inspection
Start date: 2021-05-28, end date: 2021-06-03, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the grillage device b/s 1-6 (during the production of works), installation of concrete below 0.000 b/s 1-6 (during the production of works), installation of concrete above 0.000 b/s 1-6 (during the production of works) and the construction materials used during construction, reconstruction of the capital construction facility, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (taking into account the changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) the information model (if the formation and the maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping a capital construction facility with metering devices for energy resources used. 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 742100049711
Unscheduled inspection
Start date: 2021-03-12, end date: 2021-03-18, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the work on the organization of the construction site, earthworks, works on the installation of a pile field (in the course of work) and the construction materials used during construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of this Code (taking into account the changes made to the project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of this Code) and (or) the information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities, on which energy efficiency requirements do not apply) and the requirements for equipping a capital construction facility with metering devices for energy resources used; 2. Availability of a building permit. 3. Compliance with the requirements of Parts 2.3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.