Found 4 inspections:

# 362005152943
Unscheduled inspection
Start date: 2020-09-30, end date: 2020-10-16, duration: 13
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Voronezhskoi oblasti
Purpose of inspection: This audit is carried out in order to implement the program of inspections during the construction of a capital construction facility developed on the basis of a notice of the beginning of construction reconstruction The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including the requirements of project documentation, committed by the developer, the technical customer, as well as the person carrying out construction reconstruction on the basis of an agreement with the developer or the technical customer is compliance with mandatory requirements or requirements established by municipal legal acts


# 342005239499
Unscheduled inspection
Start date: 2020-11-27, end date: 2020-12-10, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: In order to assess the compliance of activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation legislation of the Russian Federation in the field of environmental protection, fire safety requirements and sanitary and epidemiological welfare of the population of the project documentation, the task of this audit is to prevent identify and suppress violations of the legislation of the Russian Federation of the project documentation, The subject of this audit is compliance with mandatory requirements in relation to the compliance of work and applied construction materials in the process of construction reconstruction of a capital construction facility as well as the results of such work to the requirements approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation hereinafter the Code of Design Documentation, taking into account the changes made to the design documentation in accordance with parts 38 and 39 of Article 49 of the Code and or the information model if the formation and maintenance of information models are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for used energy resources, availability of a construction permit, and compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 341904144548
Unscheduled inspection
Start date: 2019-12-24, end date: 2019-12-27, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation and project documentationproblems prevention detection and suppression of violations of the legislation of the Russian Federation and project documentationsubject fulfillment of the instruction dated November 22, 2019 4205 issued to the Company on the elimination of violations committed during the construction of the Facility


# 341903942208
Unscheduled inspection
Start date: 2019-11-12, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.