# 77190803479820
Unscheduled inspection
Start date: 2019-08-16, end date: 2019-08-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803451118
Unscheduled inspection
Start date: 2019-07-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803433248
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, fulfillment by the person carrying out the construction requirements of part 3 of Article 52 of the Urban Planning Code
# 77170701906804
Unscheduled inspection
Start date: 2017-08-21, end date: 2017-08-23, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77170701728190
Unscheduled inspection
Start date: 2017-06-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160701050790
Unscheduled inspection
Start date: 2016-10-27, end date: 2016-11-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the capital construction facility with the requirements of technical regulations and project documentation on the basis of the approved verification program, prevention of detection and suppression of violations of technical regulations and project documentation committed by the audited person, compliance of work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for used energy resources
# 77160700823292
Unscheduled inspection
Start date: 2016-09-27, end date: 2016-09-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii istecheniya sroka ispolneniya yuridicheskim licom individualnym predprinimatelem vydannogo organom gosudarstvennogo stroitelnogo nadzora predpisaniya ob ustranenii vyyavlennogo narusheniya obyazatelnyh trebovaniipreduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiproverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 977616 ot 15092016
# 77160700402862
Unscheduled inspection
Start date: 2016-09-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160601697609
Unscheduled inspection
Start date: 2016-07-12, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: