# 912100143385
Unscheduled inspection
Start date: 2021-04-27, end date: 2021-05-04, duration: —
Authority: Gosudarstvennyi komitet po gosudarstvennoi registracii i kadastru Respubliki Krym
Purpose of inspection: This audit is conducted in order to perform state functions for the implementation of state land supervision on the basis of an administrative survey report containing information on the presence of signs of violations of the requirements of the legislation of the Russian Federation, for which the legislation of the Russian Federation provides for administrative and other liability.
The objectives of this audit are to verify compliance with the requirements of land legislation when using a land plot located at the address: Republic of Crimea, Simferopol, M. Vasilevsky St. - Valdayskaya St., cadastral number 90:22:010108:335.
The subject of the audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts (Part 3 Article 71 of the Land Code of the Russian Federation);
# 911800304599
Unscheduled inspection
Start date: 2018-05-10, end date: 2018-06-07, duration: —
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora Respubliki Krym
Purpose of inspection: The purpose is to verify the information contained in the documents of a legal personindividual entrepreneur establishing the organizational and legal form of the UIP documents used in the implementation of the activities of the UIP and related to the fulfillment of mandatory requirements Tasks Compliance with mandatory requirements of the Urban Planning Code of the Russian Federation Subject compliance with mandatory requirements
# 82170701679554
Unscheduled inspection
Start date: 2017-06-06, end date: 2017-06-13, duration: —
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora Respubliki Krym
Purpose of inspection: The purpose is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, other regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources, the need for a construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code. the Code of the Russian Federation during the construction of a capital construction facility tasks prevention detection and suppression of violations of the law on the contract with the developer or the customer committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, violations of the law on urban development, including technical regulations and design documentationsubject compliance with mandatory requirements for the prevention of natural and man-made emergencies
# 82170701593819
Unscheduled inspection
Start date: 2017-05-15, end date: 2017-05-19, duration: —
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora Respubliki Krym
Purpose of inspection: The purpose is to verify the compliance of the work and the construction materials used during the construction of a capital construction facility, as well as the results of such work with the requirements of technical regulations, other regulations and design documentation, the availability of a construction permit, the fulfillment of the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation during the construction of a capital construction facility, the compliance of the work and the construction materials used during the construction process reconstruction of the capital construction facility as well as the results of such work to the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources, as well as documents confirming the right to perform construction work when registering a declaration on the commencement of construction work on objects belonging to the IIII category of complexity or when issuing a permit for construction works on objects belonging to the IV and V categories of complexity of meeting the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation are aimed at preventing the detection and suppression of violations of legislation on urban planning activities committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, including technical regulations and project documentation. natural and man-made situations