Found 5 inspections:

# 521902872920
Unscheduled inspection
Start date: 2019-07-16, end date: 2019-07-17, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the audit is conducted in order to assess the facts set out in the collective appeal of residents of 23 Yaroslavskaya Street Nizhny Novgorod vh OG0013744319 dated 26062019, as well as to assess the compliance of the work and the construction materials used during construction, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements The requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements established by parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian FederationThe task of verification is to monitor compliance with the requirements of urban planning legislation and project documentation.


# 521902844861
Unscheduled inspection
Start date: 2019-07-05, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection:


# 521902631757
Unscheduled inspection
Start date: 2019-04-09, end date: 2019-04-10, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the audit is conducted in order to assess the facts stated in the collective appeal of residents of 23 Yaroslavskaya Street Nizhny Novgorod vh OG5191636419 dated 28032019, as well as to assess the compliance of the work and the construction materials used during construction, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements The requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements set out in parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation do not apply. The task of verification is to monitor compliance with the requirements of urban planning legislation and project documentation.


# 521800429924
Unscheduled inspection
Start date: 2018-03-15, end date: —, duration:
Authority:
Purpose of inspection:


# 521800230835
Unscheduled inspection
Start date: 2018-03-29, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.