Found 13 inspections:

# 002004187956
Unscheduled inspection
Start date: 2020-01-16, end date: —, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001802155459
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-12-21, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to implement the Inspection Program approved by the Deputy head of the Siberian Department of Rostechnadzor Kolegov DV from 02032018 365, the objectives of this inspection are to prevent identify and suppress violations of the legislation on urban development activities by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this inspection is the compliance of the work and the applied building materials and the results during the construction of the capital construction facility "Arrangement of the Karai oil field Kustovaya pad 4" as well as the results of such work of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources availability of a construction permit compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation


# 001802155439
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-12-21, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to implement the Inspection Program approved by Kolegov DV, Deputy Head of the Siberian Department of Rostechnadzor, dated 02032018 364, the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the developer, the customer, and the person carrying out construction on the basis of a contract with the developer or customer, hereinafter referred to as the contractor. The subject of this inspection is the compliance of the work performed and the construction materials used and the results during the construction of the capital construction facility "Development of the Karai oil field Kustovaya site 3" as well as the results of such work on project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation


# 001801756520
Unscheduled inspection
Start date: 2018-10-01, end date: —, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001801756503
Unscheduled inspection
Start date: 2018-10-01, end date: —, duration:
Authority:
Purpose of inspection:


# 002004187956
Unscheduled inspection
Start date: 2020-01-16, end date: 2020-02-12, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to implement the Inspection Program approved by the deputy head of the Siberian Department of Rostechnadzor Kolegov DV 365the task of this inspection is to prevent identify and suppress violations of the legislation on urban development activities by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer of the project documentation, the subject of this inspection is to verify the compliance of the work and the construction materials used during the construction of the facility capital construction "Development of the Karai oil field Kustovaya pad 4" located at the address Tomsk region Kargasoksky district Karai oil field as well as the results of such work to the requirements of the project documentation approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 3_8 and 3_9 of Article 49 The Urban Planning Code of the Russian Federation and or the information model, if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit, requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation


# 002004187918
Unscheduled inspection
Start date: 2020-01-16, end date: 2020-02-12, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to implement the Inspection Program approved by the deputy head of the Siberian Department of Rostechnadzor Kolegov DV 364, the task of this inspection is to prevent, identify and suppress violations of the legislation on urban planning activities by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer, the subject of this inspection is to verify the compliance of the work and the construction materials used during the construction of the facility capital construction "Development of the Karai oil field Kustovaya pad 3" located at the address Tomsk region Kargasoksky district Karai oil field as well as the results of such work to the requirements of the project documentation approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 3_8 and 3_9 of Article 49 The Urban Planning Code of the Russian Federation and or the information model, if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements of equipping the capital construction facility with metering devices for energy resources used, availability of a construction permit, requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation


# 001802155459
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-12-21, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to implement the Inspection Program approved by the Deputy head of the Siberian Department of Rostechnadzor Kolegov DV from 02032018 365, the objectives of this inspection are to prevent identify and suppress violations of the legislation on urban development activities by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, the subject of this inspection is the compliance of the work and the applied building materials and the results during the construction of the capital construction facility "Arrangement of the Karai oil field Kustovaya pad 4" as well as the results of such work of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources availability of a construction permit compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation


# 001802155439
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-12-21, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to implement the Inspection Program approved by Kolegov DV, Deputy Head of the Siberian Department of Rostechnadzor, dated 02032018 364, the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development by the developer, the customer, and the person carrying out construction on the basis of a contract with the developer or customer, hereinafter referred to as the contractor. The subject of this inspection is the compliance of the work performed and the construction materials used and the results during the construction of the capital construction facility "Development of the Karai oil field Kustovaya site 3" as well as the results of such work on project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation


# 001801756520
Unscheduled inspection
Start date: 2018-10-01, end date: 2018-10-08, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to monitor the implementation of regulation C2518068 of 25062018 on the elimination of identified offenses, the deadline for which expired on 24092018, the objectives of this audit are to establish the facts of compliance by USSR LLC with regulation C2518068 of 25062018. The subject of this audit is the implementation of regulation C2518068 of 25062018 of the state construction supervision authority


# 001801756503
Unscheduled inspection
Start date: 2018-10-01, end date: 2018-10-08, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to monitor the implementation of regulation C2518062 dated 08062018 on the elimination of identified offenses, the deadline for which expired on January 100, 2018, the objectives of this audit are to establish the facts of compliance by USSR LLC with regulation C2518062 dated 08062018. The subject of this audit is the implementation of regulation C2518062 dated 08062018 of the state construction supervision authority


# 001800343672
Unscheduled inspection
Start date: 2018-05-14, end date: 2018-06-08, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to monitor the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the reconstruction of a capital construction facility based on the inspection program approved by the Deputy head of the Siberian Directorate of Rostechnadzor dated 02032018 364, the objectives of this audit are to prevent identify and suppress violations committed by the developer, the customer, and the person carrying out the construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, violations of the legislation on urban development, including the requirements of the technical regulations of the project documentation, the subject of this audit is the compliance of the work performed and the construction materials used and the results during the construction of the capital construction facility "Development of the Karai oil field Kustovaya site 3" as well as the results of such work with the requirements of the technical regulations of the project documentation including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements of parts 23 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation.


# 001800343801
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-06-25, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to monitor the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility based on the inspection program approved by the Deputy head of the Siberian Department of Rostechnadzor dated 02032018, the objectives of this inspection are to prevent identify and suppress violations committed by the developer, the customer, and the person carrying out the construction on the basis of an agreement with the developer or the customer, hereinafter referred to as the contractor, violations of the legislation on urban planning activities, including the requirements of the technical regulations of the project documentation, the subject of this audit is the compliance of the work performed and the construction materials used and the results during the construction of the capital construction facility, as well as the results of such work with the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and equipment capital construction facility with metering devices for used energy resources availability of a construction permit compliance with the requirements of parts 23 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation


Information about inspections