# 782100350811
Unscheduled inspection
Start date: 2021-07-09, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: g) proverki zaversheniya rabot po osuschestvleniyu stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, ukazannogo v izveschenii zastroischika (tehnicheskogo zakazchika) ob okonchanii stroitelstva
vh. № 03-5422/2019-18 ot 24.06.2021;
a) soblyudenie obyazatelnyh trebovanii, v tom chisle:
sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov;
# 782100140552
Unscheduled inspection
Start date: 2021-03-18, end date: 2021-04-14, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: ) soblyudenie obyazatelnyh trebovanii, v tom chisle:
sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov;
nalichie razresheniya na stroitelstvo;
vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii;
b) vypolnenie predpisanii komiteta gosudarstvennogo stroitelnogo nadzora i
gosudarstvennoi ekspertizy Leningradskoi oblasti;
v) provedenie meropriyatii:
po predotvrascheniyu prichineniya vreda zhizni, zdorovyu grazhdan, vreda zhivotnym, rasteniyam, okruzhayuschei srede;
po preduprezhdeniyu vozniknoveniya chrezvychainyh situacii prirodnogo i tehnogennogo haraktera;
po likvidacii posledstvii prichineniya takogo vreda
# 782100045529
Unscheduled inspection
Start date: 2021-02-01, end date: 2021-03-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel: proverka zaversheniya rabot po osuschestvleniyu stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, ukazannogo v izveschenii zastroischika (tehnicheskogo zakazchika) ob okonchanii stroitelstva. Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii, v tom chisle: sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov, proektnoi dokumentacii, v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov, vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii; zadachami nastoyaschei proverki yavlyayutsya: preduprezhdenie, vyyavlenie i presechenie dopuschennyh zastroischikom, tehnicheskim zakazchikom (licom, osuschestvlyayuschim stroitelstvo) narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, v tom chisle tehnicheskih reglamentov, i proektnoi dokumentacii.
# 782100083307
Unscheduled inspection
Start date: 2021-02-01, end date: 2021-03-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: proverki zaversheniya rabot po osuschestvleniyu stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, ukazannogo v izveschenii zastroischika (tehnicheskogo zakazchika) ob okonchanii stroitelstva
a) soblyudenie obyazatelnyh trebovanii, v tom chisle:
sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov;
nalichie razresheniya na stroitelstvo;
vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3.1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii;
b) vypolnenie predpisanii komiteta gosudarstvennogo stroitelnogo nadzora i
gosudarstvennoi ekspertizy Leningradskoi oblasti;
v) provedenie meropriyatii:
po predotvrascheniyu prichineniya vreda zhizni, zdorovyu grazhdan, vreda zhivotnym, rasteniyam, okruzhayuschei srede;
po preduprezhdeniyu vozniknoveniya chrezvychainyh situacii prirodnogo i tehnogennogo haraktera;
po likvidacii posledstvii prichineniya takogo vreda.
# 782000031435
Unscheduled inspection
Start date: 2020-12-17, end date: 2021-01-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used to meet the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction
# 472004474527
Unscheduled inspection
Start date: 2020-08-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472004406285
Unscheduled inspection
Start date: 2020-05-07, end date: 2020-06-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for energy resources used to meet the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction
# 472004412041
Unscheduled inspection
Start date: 2020-05-13, end date: 2020-06-09, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction
# 471903901448
Unscheduled inspection
Start date: 2019-10-31, end date: 2019-11-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 471902637457
Unscheduled inspection
Start date: 2019-04-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902545598
Unscheduled inspection
Start date: 2019-02-28, end date: 2019-03-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471802306815
Unscheduled inspection
Start date: 2018-12-13, end date: 2019-01-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel proverka zaversheniya rabot po osuschestvleniyu stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva ukazannogo v izveschenii zastroischika tehnicheskogo zakazchika ob okonchanii stroitelstva Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii v tom chisle sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov vypolnenie trebovanii chastei 2 3 i 31 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 471801563898
Unscheduled inspection
Start date: 2018-10-03, end date: 2018-10-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471801563901
Unscheduled inspection
Start date: 2018-10-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471800614466
Unscheduled inspection
Start date: 2018-08-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471800567468
Unscheduled inspection
Start date: 2018-07-19, end date: 2018-08-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471800197341
Unscheduled inspection
Start date: 2018-03-12, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 471800176918
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility implementation of the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 47170802985128
Unscheduled inspection
Start date: 2017-12-13, end date: 2018-01-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation
# 47170701450921
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-04-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel proverki rabot po nachalu stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva ukazannogo v izveschenii zastroischika ili tehnicheskogo zakazchika o nachale stroitelstva rekonstrukcii Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii v tom chisle sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 47170701450909
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-04-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel proverki rabot po nachalu stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva ukazannogo v izveschenii zastroischika ili tehnicheskogo zakazchika o nachale stroitelstva rekonstrukciiPredmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii v tom chislesootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovvypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii