Found 11 inspections:

# 001902796612
Unscheduled inspection
Start date: 2019-06-17, end date: 2019-06-28, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of the instruction of the Siberian Directorate of Rostechnadzor 3401PKIP14 dated 26022019, the deadline for which has expired. The tasks of verification are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations, rules for the technical operation of heat supply facilities and heat-consuming installations and labor protection regulations


# 00170802318732
Unscheduled inspection
Start date: 2017-09-12, end date: 2017-09-29, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the progress of preparations for work in the autumn winter period of 2017-2018 on the basis of Order No. 256 of the Federal Service for Environmental Technological and Nuclear Supervision dated 10072017 "On monitoring the progress of preparation of electric power and Heat supply facilities for work in the autumn winter period of 2017-2018" issued on the basis of instructions from the Deputy Chairman of the Government of the Russian Federation dated June 29, 2017 DKP94194THE tasks of this audit These are inspections of the technical condition and safe operation of thermal power plants in order to monitor the progress of preparations for operation in the autumn-winter period of 2017-2018


# 00170701400553
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-02-27, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The objectives of this audit are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190 FZ "On Heat Supply", technical regulations, rules for the technical operation of heat supply facilities and heat-consuming installations, and control over the execution of the order of the Siberian Directorate of Rostechnadzor 341POZP78 dated 27092016, the deadline for which has expired


# 00160701023652
Unscheduled inspection
Start date: 2016-10-17, end date: 2016-10-21, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring the progress of preparations for the operation of Rybalovskoye Housing and Communal Services LLC in the 2016-2017 period on the basis of Order No. 229 of the Federal Service for Environmental Technological and Nuclear Supervision dated 17062016 issued pursuant to the instructions of Deputy Prime Minister of the Russian Federation DN Kozak dated 02062016 DKP93275THE objectives of this audit are the implementation of federal state energy supervision in the field of heat supply Subject to verification compliance with mandatory requirements established by the Federal Law of 27072010 g 190FZ "On Heat Supply" and other regulatory legal acts of the Russian Federation in the field of heat supply


# 001902796612
Unscheduled inspection
Start date: 2019-06-17, end date: 2019-06-28, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of the instruction of the Siberian Directorate of Rostechnadzor 3401PKIP14 dated 26022019, the deadline for which has expired. The tasks of verification are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations, rules for the technical operation of heat supply facilities and heat-consuming installations and labor protection regulations


# 001902530902
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-22, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the purpose of monitoring the implementation of the instruction of the Siberian Directorate of Rostechnadzor 3401POZP64 dated 28082018, the deadline for which has expired, the objectives of this audit are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations, rules for the technical operation of heat supply facilities and heat-consuming installations and labor protection regulations


# 001800636685
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-14, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to check the progress of preparations for the operation of Dalenergo LLC in the 2018-2019 OZP on the basis of Order No. 308 of the Federal Service for Environmental Technological and Nuclear Supervision dated 16072018 issued pursuant to the instruction of Deputy Prime Minister of the Russian Federation Vladimir Mutko dated 26062018 VMP93773. The objectives of this audit are to prevent identify and suppress violations by heat supply organizations and heating grid organizations of safety requirements in the field of heat supply regulations established by the Federal Law of 27072010 190FZ "On Heat Supply", technical regulations and rules for the technical operation of heat supply facilities and heat-consuming installations


# 001800071318
Unscheduled inspection
Start date: 2018-02-06, end date: 2018-02-13, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of the regulations of the Siberian Directorate of Rostechnadzor 3401POZP70 dated 20092017, the deadline for which has expired. The objectives of this audit are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190FZ "On Heat Supply" by technical regulations and rules for the technical operation of heat supply facilities and heat-consuming installations


# 00170802318732
Unscheduled inspection
Start date: 2017-09-12, end date: 2017-09-29, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the progress of preparations for work in the autumn winter period of 2017-2018 on the basis of Order No. 256 of the Federal Service for Environmental Technological and Nuclear Supervision dated 10072017 "On monitoring the progress of preparation of electric power and Heat supply facilities for work in the autumn winter period of 2017-2018" issued on the basis of instructions from the Deputy Chairman of the Government of the Russian Federation dated June 29, 2017 DKP94194THE tasks of this audit These are inspections of the technical condition and safe operation of thermal power plants in order to monitor the progress of preparations for operation in the autumn-winter period of 2017-2018


# 00170701400553
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-02-27, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The objectives of this audit are to prevent, identify and suppress violations by heat supply organizations and heating grid organizations of the safety requirements in the field of heat supply established by Federal Law No. 27072010 190 FZ "On Heat Supply", technical regulations, rules for the technical operation of heat supply facilities and heat-consuming installations, and control over the execution of the order of the Siberian Directorate of Rostechnadzor 341POZP78 dated 27092016, the deadline for which has expired


# 00160701023652
Unscheduled inspection
Start date: 2016-10-17, end date: 2016-10-21, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring the progress of preparations for the operation of Rybalovskoye Housing and Communal Services LLC in the 2016-2017 period on the basis of Order No. 229 of the Federal Service for Environmental Technological and Nuclear Supervision dated 17062016 issued pursuant to the instructions of Deputy Prime Minister of the Russian Federation DN Kozak dated 02062016 DKP93275THE objectives of this audit are the implementation of federal state energy supervision in the field of heat supply Subject to verification compliance with mandatory requirements established by the Federal Law of 27072010 g 190FZ "On Heat Supply" and other regulatory legal acts of the Russian Federation in the field of heat supply


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.