Found 8 inspections:

# 242101408577
Unscheduled inspection
Start date: 2021-12-01, end date: —, duration:
Authority:
Purpose of inspection:


# 242101309554
Unscheduled inspection
Start date: 2021-11-09, end date: —, duration:
Authority:
Purpose of inspection:


# 242100315099
Unscheduled inspection
Start date: 2021-08-02, end date: —, duration:
Authority:
Purpose of inspection:


# 242100246191
Unscheduled inspection
Start date: 2021-06-01, end date: —, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that: this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility, in connection with the onset of completion dates, which are subject to verification in accordance with the approved program of 08/25/2020 inspections during the construction of a capital construction facility; The objectives of this audit are to prevent, identify and suppress violations of legislation on urban development, including project documentation. 7. The subject of this audit is: 7.1. Verification of compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the design documentation in accordance with parts 3.8 and 3.9 of Article 49 Of the Urban Planning Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and equipment requirements of the capital construction facility metering devices for energy resources used; 7.2. Fulfillment of the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; 7.3. Checking the availability of a building permit.


# 242100085545
Unscheduled inspection
Start date: 2021-04-01, end date: —, duration:
Authority:
Purpose of inspection:


# 242105348222
Unscheduled inspection
Start date: 2021-02-04, end date: 2021-03-04, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that: this inspection is carried out in order to verify the fulfillment of the previously issued instruction No. 2075-ONS-3 dated 09/29/2020, on the elimination of identified violations at the specified capital construction facility, in connection with the notification received (dated 01/27/2021). No. 7) on the elimination of violations before the expiration of the period specified in the regulation. The purpose of this audit is to establish the fact of elimination of previously identified violations. 7. The subject of this audit is the fulfillment of a legal order of the body carrying out regional state construction supervision, the deadline for which expires 23.11.20, respectively.


# 242105330931
Unscheduled inspection
Start date: 2021-02-01, end date: 2021-02-26, duration: 19
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that:this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility, in connection with the onset of completion dates, which are subject to verification in accordance with the approved program dated 08/25/2020 for conducting inspections during the construction of a capital construction facility; the objectives of this inspection are to prevent, identify and suppress violations of legislation on urban development, in particular including the project documentation.7. The subject of this audit is:7.1. Verification of compliance of the work performed and the construction materials used during the construction of a capital construction facility, as well as the results of such work, with the requirements of the design documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the design documentation in accordance with parts 3.8 and 3.9 of Article 49 Of the Urban Planning Code of the Russian Federation) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and equipment requirements of the capital construction facility metering devices for energy resources used;7.2. Fulfillment of the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; 7.3. Verification of the availability of a construction permit.


# 242005241002
Unscheduled inspection
Start date: 2020-12-01, end date: 2020-12-28, duration: 20
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: To establish that this inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates that are subject to verification in accordance with the approved program from 25082020 of inspections during the construction of a capital construction facility, the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including design documentation7 The subject of this audit is 71 Verification of the compliance of the work performed and the construction materials used in the construction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation If the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction projects to which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used72 Compliance with the requirements established by parts 2 3 and 31 Article 52 of the Urban Planning Code of the Russian Federation73 Checking the availability of a construction permit