# 74170701511726
Unscheduled inspection
Start date: 2017-04-06, end date: 2017-04-12, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the installation of structures at the roof level, the installation of window blocks and building materials used in the construction of a capital construction facility, as well as the results of such work, with the requirements of technical regulations of project documentation2the presence of a construction permit 3The fulfillment of the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation