# 521902423749
Unscheduled inspection
Start date: 2019-01-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 521800657607
Unscheduled inspection
Start date: 2018-09-12, end date: 2018-09-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out in order to verify compliance with the requirements of the regulation dated 20122017 519030104402 issued to the developer MEGAPOLIS LLC for assessing the compliance of work performed and building materials used during construction with the requirements of technical regulations, norms and rules and design documentation. The task of the inspection is to monitor compliance with the requirements of urban planning legislation and other regulatory legal acts in the field of construction
# 52170802985742
Unscheduled inspection
Start date: 2017-12-19, end date: 2017-12-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out in order to verify compliance with the requirements of the regulation dated 28062017 519030104156 issued to the developer MEGAPOLIS LLC for assessing the compliance of work performed and building materials used during construction with the requirements of technical regulations, norms and rules and design documentation. The task of the inspection is to monitor compliance with the requirements of urban planning legislation and other regulatory legal acts in the field of construction