Found 14 inspections:

# 772004466798
Unscheduled inspection
Start date: 2020-07-27, end date: —, duration:
Authority:
Purpose of inspection:


# 772004344372
Unscheduled inspection
Start date: 2020-03-10, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772004237265
Unscheduled inspection
Start date: 2020-02-03, end date: —, duration:
Authority:
Purpose of inspection:


# 771904051838
Unscheduled inspection
Start date: 2019-12-05, end date: 2019-12-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer's task of verification, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check and verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903984686
Unscheduled inspection
Start date: 2019-11-20, end date: 2019-12-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify compliance with the instructions of the Moscow State Construction Supervision


# 771903734708
Unscheduled inspection
Start date: 2019-09-27, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803486429
Unscheduled inspection
Start date: 2019-08-30, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803480906
Unscheduled inspection
Start date: 2019-08-19, end date: 2019-08-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803447696
Unscheduled inspection
Start date: 2019-07-01, end date: 2019-07-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803453020
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-07-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803444470
Unscheduled inspection
Start date: 2019-06-24, end date: 2019-07-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803408350
Unscheduled inspection
Start date: 2019-05-06, end date: 2019-05-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803402919
Unscheduled inspection
Start date: 2019-04-25, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803335813
Unscheduled inspection
Start date: 2019-02-13, end date: 2019-03-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.