# 24170802919850
Unscheduled inspection
Start date: 2017-12-01, end date: 2017-12-14, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction dated 23112017 4760EN previously issued to the person being checked on the elimination of identified violations at the specified capital construction facility, the deadline for which expires on 30112017the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period 7 The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision
# 24170802921975
Unscheduled inspection
Start date: 2017-11-30, end date: —, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection:
# 24170802768697
Unscheduled inspection
Start date: 2017-10-26, end date: 2017-11-23, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: this unscheduled inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility on the basis of the received notification dated 18102017 bx 257 on the completion of the construction of the capital construction facility. The objectives of this unscheduled inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation, to verify the compliance of work performed and applied construction materials during the construction of a capital construction facility, as well as the results of such work, the requirements of technical regulations and design documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, are subject to verification of all acts regulations notices on the elimination of violations deficiencies identified during the implementation of regional state construction supervision, Checking the availability of a construction permit, Checking the availability of certificates of admission to the types of work on the construction of a capital construction facility that affect the safety of a capital construction facility
# 24170701665211
Unscheduled inspection
Start date: 2017-06-06, end date: 2017-06-20, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the instruction previously issued to the person being checked from 26042017 1199DPO on the elimination of identified violations at the specified capital construction facility, the deadline for which expires 05062017 the objectives of this inspection are to establish the fact of elimination of previously identified violations and to verify the work actually performed in accordance with the prescribed measures within the prescribed period. The subject of this inspection is the fulfillment of the instruction of the body carrying out Regional State construction supervision
# 24170701492984
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-28, duration: —
Authority: Sluzhba stroitelnogo nadzora i zhilischnogo kontrolya Krasnoyarskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state construction supervision during the construction of the specified capital construction facility in connection with the timing of completion of work that is subject to inspection in accordance with the approved program of 10092014 inspections during the construction of the capital construction facility The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and The subject of this audit is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, and to verify the availability of a certificate of admission to the types of work on the construction of the capital construction facility that provide impact on the safety of a capital construction facility