Found 13 inspections:

# 002005221650
Unscheduled inspection
Start date: 2020-11-12, end date: —, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 002005195569
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-10-30, duration: 5
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the previously issued instruction from 31072020 3302215 on the basis of receipt by the Ural Office of Rostechnadzor of a request from Electric Grid Company LLC to conduct an inspection in order to recognize the prescription as fulfilled in order from 21092020 33016303 The objectives of this inspection are to take measures to control the elimination of violations specified in paragraphs of the instruction from 31072020 3302215the subject of this inspection is to comply with the instructions state control and supervision bodies


# 002004461050
Unscheduled inspection
Start date: 2020-07-23, end date: 2020-07-31, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 08072020267 "On monitoring the progress of preparation of electric power and Heat supply facilities for operation in the autumn-winter period of 20202021" issued on the basis of the instruction of the Government of the Russian Federation dated 03072020 YUBP97109 order of the Ural Rostechnadzor Department dated 09072020 PR332278o "On monitoring the progress of preparation of Electric Power and Heat Supply Facilities heat supply for operation in the autumn-winter period of 2020-2021", which approved the Schedule of inspections of electric power and heat supply facilities for which preparations for the heating period of 2020-2021 are monitored. The objectives of this audit are to prevent, identify and suppress violations in the implementation of measures to monitor compliance with safety requirements in the thermal power industry. The subject of this audit is the observance by Electric Grid Company LLC of mandatory requirements


# 001902938901
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-16, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: execution of the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 04072019 262 "On monitoring the progress of preparation of electric Power facilities for operation in the autumn-winter period 2019-2020" issued on the basis of the order of the Government of the Russian Federation dated 18062019 DKP94982 of the Order of the Ural Department of the Federal Service for Environmental Technological and Nuclear Supervision dated 05072019 484 "On the organization of the course of preparation of electric Power Industry entities to work in the autumn-winter period 2019-2020"


# 00150601357337
Unscheduled inspection
Start date: 2015-11-24, end date: 2015-11-26, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the fulfillment by LLC "Electric Grid Company" of the points of the previously issued instruction on the elimination of identified violations


# 00150600032637
Unscheduled inspection
Start date: 2015-08-10, end date: —, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the progress of preparation of electric heat supply organizations for work in the autumn-winter period 20152016 in accordance with the order of the Federal Service for Environmental Technological and Nuclear Supervision 237 dated 23062015 On monitoring the progress of preparation and assessment of the readiness of electric power and heat supply facilities for work in the autumn-winter period 20152016


# 002005221650
Unscheduled inspection
Start date: 2020-11-12, end date: 2020-11-13, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the previously issued instruction from 19112019 H5846 on the basis of receipt by the Ural Office of Rostechnadzor of a request from LLC "Electric Grid Company" to conduct an inspection in order to recognize the order fulfilled in the order from 27102020 33018692 The purpose of this inspection is to take measures to control the elimination of violations specified in the paragraphs of the instruction from 19112019 H5846the subject of this inspection is to comply with the instructions state control and supervision bodies


# 002005195569
Unscheduled inspection
Start date: 2020-10-26, end date: 2020-10-30, duration: 5
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the previously issued instruction from 31072020 3302215 on the basis of receipt by the Ural Office of Rostechnadzor of a request from Electric Grid Company LLC to conduct an inspection in order to recognize the prescription as fulfilled in order from 21092020 33016303 The objectives of this inspection are to take measures to control the elimination of violations specified in paragraphs of the instruction from 31072020 3302215the subject of this inspection is to comply with the instructions state control and supervision bodies


# 002004461050
Unscheduled inspection
Start date: 2020-07-23, end date: 2020-07-31, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 08072020267 "On monitoring the progress of preparation of electric power and Heat supply facilities for operation in the autumn-winter period of 20202021" issued on the basis of the instruction of the Government of the Russian Federation dated 03072020 YUBP97109 order of the Ural Rostechnadzor Department dated 09072020 PR332278o "On monitoring the progress of preparation of Electric Power and Heat Supply Facilities heat supply for operation in the autumn-winter period of 2020-2021", which approved the Schedule of inspections of electric power and heat supply facilities for which preparations for the heating period of 2020-2021 are monitored. The objectives of this audit are to prevent, identify and suppress violations in the implementation of measures to monitor compliance with safety requirements in the thermal power industry. The subject of this audit is the observance by Electric Grid Company LLC of mandatory requirements


# 001903985648
Unscheduled inspection
Start date: 2019-11-19, end date: 2019-11-22, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the fulfillment of the previously issued instruction dated 16082019 H3698, the deadline for which has expired. The objectives of this inspection are to take measures to control the elimination of violations specified in paragraphs of the instruction dated 16082019 H3698. The purpose of this inspection is to comply with the instructions of the state control and supervision authorities


# 001902938901
Unscheduled inspection
Start date: 2019-08-12, end date: 2019-08-16, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: execution of the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 04072019 262 "On monitoring the progress of preparation of electric Power facilities for operation in the autumn-winter period 2019-2020" issued on the basis of the order of the Government of the Russian Federation dated 18062019 DKP94982 of the Order of the Ural Department of the Federal Service for Environmental Technological and Nuclear Supervision dated 05072019 484 "On the organization of the course of preparation of electric Power Industry entities to work in the autumn-winter period 2019-2020"


# 00150601357337
Unscheduled inspection
Start date: 2015-11-24, end date: 2015-11-26, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the fulfillment by LLC "Electric Grid Company" of the points of the previously issued instruction on the elimination of identified violations


# 00150600032637
Unscheduled inspection
Start date: 2015-08-10, end date: —, duration:
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the progress of preparation of electric heat supply organizations for work in the autumn-winter period 20152016 in accordance with the order of the Federal Service for Environmental Technological and Nuclear Supervision 237 dated 23062015 On monitoring the progress of preparation and assessment of the readiness of electric power and heat supply facilities for work in the autumn-winter period 20152016


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.