# 77190803320616
Unscheduled inspection
Start date: 2019-01-28, end date: 2019-02-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: Celi provedenie meropriyatii po kontrolyu v svyazi s postupleniem izvescheniya zastroischika zakazchika na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narushenii ot 11012019 bnZadachi preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmet proverki proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 1006418 ot 07122018
# 77180803272094
Unscheduled inspection
Start date: 2018-11-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803191423
Unscheduled inspection
Start date: 2018-08-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803180195
Unscheduled inspection
Start date: 2018-07-11, end date: 2018-07-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used