# 782101316166
Unscheduled inspection
Start date: 2021-11-08, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: v) proverki ustraneniya narushenii obyazatelnyh trebovanii, ukazannyh v izveschenii lica, osuschestvlyayuschego stroitelstvo, ob ustranenii vyyavlennyh narushenii
vh. № 03-6384/2018-48 ot 29.09.2021
z) proverki ispolneniya vydannogo predpisaniya ob ustranenii vyyavlennogo narusheniya № P540-DI-21 ot "06" avgusta 2021 goda, srok ispolneniya kotorogo istek "30" sentyabrya 2021 goda;
b) vypolnenie predpisanii komiteta gosudarstvennogo stroitelnogo nadzora i
gosudarstvennoi ekspertizy Leningradskoi oblasti;
# 782100390802
Unscheduled inspection
Start date: 2021-07-29, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 472005253252
Unscheduled inspection
Start date: 2020-11-30, end date: 2020-12-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the completion of the work provided for in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 472004283779
Unscheduled inspection
Start date: 2020-02-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471904104773
Unscheduled inspection
Start date: 2019-12-12, end date: 2020-01-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to meet the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction, the purpose of checking the execution of the issued instruction on the elimination of violations identified by the subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State Expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction, including technical regulations and design objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction in including technical regulations and project documentation
# 471902977404
Unscheduled inspection
Start date: 2019-08-19, end date: 2019-09-13, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to meet the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction, the purpose of checking the execution of the issued instruction on the elimination of violations identified by the subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State Expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction, including technical regulations and design objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction in including technical regulations and project documentation
# 471902707819
Unscheduled inspection
Start date: 2019-05-13, end date: 2019-06-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471801940328
Unscheduled inspection
Start date: 2018-10-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471800567463
Unscheduled inspection
Start date: 2018-07-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471800251052
Unscheduled inspection
Start date: 2018-03-29, end date: —, duration: —
Authority: —
Purpose of inspection: