Found 100 inspections:

# 162004626165
Unscheduled inspection
Start date: 2020-09-30, end date: 2020-10-02, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 11062020 case 121120140026 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162101535186
Unscheduled inspection
Start date: 2021-12-30, end date: —, duration:
Authority:
Purpose of inspection:


# 162101404540
Unscheduled inspection
Start date: 2021-12-01, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162101489461
Unscheduled inspection
Start date: 2021-12-21, end date: 2021-01-29, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, design documentation, other normative acts (norms and rules), to determine the fact of execution of the order, as well as to draw up an act on the elimination of violations (execution of the order), based on the notification received by the Inspection dated 10.12.2021 No. 14041 on the elimination of violations during construction, reconstruction of the capital construction facility, which were ordered to be eliminated within the time limit established by Regulation No. 12-12/1109-02 dated 12.11.2021, before 12.12.2021 and the expiration of the deadline for the execution of regulation No. 12-12/1109-02 dated 12.11.2021, the deadline for which expired on 12.12.2021. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts;


# 162101393647
Unscheduled inspection
Start date: 2021-11-30, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162101393949
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration:
Authority:
Purpose of inspection:


# 162101393421
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0070. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this review is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162101393307
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration:
Authority:
Purpose of inspection:


# 162101393870
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0072. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this review is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162101393495
Unscheduled inspection
Start date: 2021-11-29, end date: —, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0071. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this review is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162101301900
Unscheduled inspection
Start date: 2021-11-08, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162101172239
Unscheduled inspection
Start date: 2021-10-14, end date: —, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 10.12.2018 case No. 12-11-2018/0124. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162101252437
Unscheduled inspection
Start date: 2021-10-22, end date: —, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05.10.2018 case No. 12-11-2018/0106. The objectives of this audit are to prevent, as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100719993
Unscheduled inspection
Start date: 2021-09-13, end date: —, duration:
Authority:
Purpose of inspection:


# 162100719688
Unscheduled inspection
Start date: 2021-09-13, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order dated 07/22/2021 No. 12-12/0611-02, the deadline for which expired on 08/20/2021; 07/22/2021 No. 12-12/0611-01, the deadline for which expired on 08/20/2021 and drawing up an act based on the results of the inspection. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is the fulfillment of the instructions of the state control (supervision) bodies, municipal control bodies.


# 162100994739
Unscheduled inspection
Start date: 2021-09-28, end date: 2021-02-12, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 01/23/2019 case No. 12-11-2019/0005. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): ☑ compliance with mandatory requirements and (or) requirements established by municipal legal acts;


# 162100423279
Unscheduled inspection
Start date: 2021-08-12, end date: 2021-01-29, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the fact of execution of the order dated 06/24/2021 No.12-12/0576-01, the deadline for which expired on 07/29/2021 and drawing up an act based on the results of the check. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with the instructions of state control (supervision) bodies, municipal control bodies;


# 162100512875
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0073. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100512019
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration:
Authority:
Purpose of inspection:


# 162100512327
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration: 9
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0072. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100512160
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration:
Authority:
Purpose of inspection:


# 162100505664
Unscheduled inspection
Start date: 2021-08-23, end date: —, duration:
Authority:
Purpose of inspection:


# 162100366339
Unscheduled inspection
Start date: 2021-08-02, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162100516985
Unscheduled inspection
Start date: 2021-08-20, end date: —, duration:
Authority:
Purpose of inspection:


# 162100516967
Unscheduled inspection
Start date: 2021-08-20, end date: —, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 01/21/2019 case No. 12-11-2019/0010. The objectives of this audit are to prevent, as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer.The subject of this review is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100516997
Unscheduled inspection
Start date: 2021-08-20, end date: —, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 01/21/2019 case No. 12-11-2019/0008. The objectives of this audit are to prevent, as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer.The subject of this review is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100344915
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162100336114
Unscheduled inspection
Start date: 2021-07-06, end date: —, duration:
Authority:
Purpose of inspection:


# 162100336232
Unscheduled inspection
Start date: 2021-07-06, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0073. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100336185
Unscheduled inspection
Start date: 2021-07-06, end date: —, duration:
Authority:
Purpose of inspection:


# 162100335931
Unscheduled inspection
Start date: 2021-07-06, end date: —, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/22/2021 case No. 17-04-2020/0069. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100338562
Unscheduled inspection
Start date: 2021-07-07, end date: —, duration:
Authority:
Purpose of inspection:


# 162100338507
Unscheduled inspection
Start date: 2021-07-07, end date: —, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, design documentation, other normative acts (norms and rules), as well as to draw up an act on the elimination of violations, based on the notification received by the Inspection dated 07/02/2021 No. 6888 on the elimination of violations during construction, reconstruction of a capital construction facility, which were ordered to be eliminated within the period established by the regulation dated 06/18/2021 No. 17-12/0202-01, until 07/16/2021. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with the instructions of state control (supervision) bodies, municipal control bodies.


# 162100338463
Unscheduled inspection
Start date: 2021-07-07, end date: —, duration:
Authority:
Purpose of inspection:


# 162100338364
Unscheduled inspection
Start date: 2021-07-07, end date: —, duration:
Authority:
Purpose of inspection:


# 162100335996
Unscheduled inspection
Start date: 2021-07-04, end date: —, duration:
Authority:
Purpose of inspection:


# 162100297874
Unscheduled inspection
Start date: 2021-06-18, end date: 2021-01-29, duration: 6
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 06/11/2021 case No. 12-04-2021/0052. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts;


# 162100315765
Unscheduled inspection
Start date: 2021-06-29, end date: 2021-03-30, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05.10.2020 case No. 12-11-2019/0020. The objectives of this audit are to prevent, as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100232688
Unscheduled inspection
Start date: 2021-06-01, end date: —, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 10.12.2018 case No. 12-11-2018/0124. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100301151
Unscheduled inspection
Start date: 2021-06-21, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162100298528
Unscheduled inspection
Start date: 2021-06-21, end date: —, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the fact of execution of the order dated 04/21/2021 No.12-12/0359-01, the deadline for which expired on 05/17/2021 and drawing up an act based on the results of the check. The objectives of this audit are to prevent, as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer. The subject of this audit is the fulfillment of the instructions of the state control (supervision) bodies, municipal control bodies.


# 162100211389
Unscheduled inspection
Start date: 2021-05-17, end date: —, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the fact of execution of the order dated 02/26/2021 No. 12-12/0176-01, the deadline for which expired on 04/02/2021 and drawing up an act based on the results of the check. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is: compliance with the instructions of state control (supervision) bodies, municipal control bodies


# 162100160487
Unscheduled inspection
Start date: 2021-04-19, end date: 2021-04-30, duration: 10
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the compliance of the completed works, the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as for the purpose of drawing up an act of verification of the completed construction facility, in accordance with the notification received by the Inspection dated 04/06/2021 No. 3182 on the completion of the construction of the capital construction facility. prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. compliance with mandatory requirements and (or) requirements established by municipal legal acts


# 162100153190
Unscheduled inspection
Start date: 2021-04-16, end date: 2021-04-21, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05.10.2018 case No. 12-11-2018/0106.The objectives of this audit are to prevent, as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100138645
Unscheduled inspection
Start date: 2021-04-12, end date: 2021-04-16, duration: 5
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 01/27/2021 case No. 12-11-2014/0026. prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and design documentation documentation. compliance with mandatory requirements and (or) requirements established by municipal legal acts


# 162100139948
Unscheduled inspection
Start date: 2021-04-13, end date: 2021-04-16, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05/23/2018 case No. 12-11-2018/0048.The objectives of this audit are to prevent, as well as to identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer.The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100139972
Unscheduled inspection
Start date: 2021-04-13, end date: 2021-04-16, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05/23/2018 case No. 12-11-2018/0050.The objectives of this audit are to prevent, as well as to identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer.The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100139960
Unscheduled inspection
Start date: 2021-04-13, end date: 2021-04-16, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05/23/2018 case No. 12-11-2018/0049.The objectives of this audit are to prevent, as well as to identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation.The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100186020
Unscheduled inspection
Start date: 2021-04-29, end date: —, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 01/21/2019 case No. 12-11-2019/0004. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts;


# 162100103529
Unscheduled inspection
Start date: 2021-03-31, end date: 2021-04-05, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 03/11/2019 case No. 12-11-2019/0031. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with mandatory requirements and (or) requirements established by municipal legal acts;


# 162100096583
Unscheduled inspection
Start date: 2021-03-26, end date: 2021-04-09, duration: 11
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 05.10.2020 case No. 12-11-2019/0020. The objectives of this audit are to prevent, as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100020122
Unscheduled inspection
Start date: 2021-02-20, end date: 2021-02-24, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2, 3 and 3.1 of Article 52 The Urban Planning Code of the Russian Federation, in accordance with the inspection program dated 10.12.2018 case No. 12-11-2018/0124. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements and (or) requirements established by municipal legal acts.


# 162100001820
Unscheduled inspection
Start date: 2021-02-09, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162105316999
Unscheduled inspection
Start date: 2021-01-26, end date: 2021-01-27, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this inspection is carried out in order to determine the fact of execution of the order dated 03.12.2020 No. 12-12/1159-01, the deadline for which expired on 15.01.2021 and drawing up an act based on the results of the inspection. The objectives of this audit are: prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The subject of this audit is (select the appropriate one): compliance with the instructions of state control (supervision) bodies, municipal control bodies;


# 162005281038
Unscheduled inspection
Start date: 2020-12-21, end date: 2020-12-21, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the fact of execution of the order dated 28102020 1212103101, the deadline for which expired 30112020 28102020 1212103102, the deadline for which expired 30112020 and drawing up an act based on the results of the check, the tasks of this check are to prevent as well as identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of a capital construction facility according to the requirements of technical regulations, other regulatory legal acts and project documentation, the subject of this audit is the fulfillment of the instructions of state control bodies, supervision of municipal control bodies


# 162005281035
Unscheduled inspection
Start date: 2020-12-21, end date: 2020-12-21, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order dated 28102020 1212103001, the deadline for which expired 30112020 28102020 1212103002, the deadline for which expired 30112020 and drawing up an act based on the results of the inspection, the tasks of this inspection are to prevent as well as identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of the capital construction facility The subject of this audit is the fulfillment of the requirements of the state control bodies supervision of municipal control bodies


# 162005279465
Unscheduled inspection
Start date: 2020-12-21, end date: 2020-12-21, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order dated 27102020 1212102902, the term of which expired 27112020 27102020 1212102901, the term of which expired 27112020 and drawing up an act based on the results of the inspection, the tasks of this inspection are the prevention as well as the identification and suppression of violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of the capital construction facility The subject of this inspection is the fulfillment of the requirements of the state control bodies supervision of municipal control bodies


# 162005256808
Unscheduled inspection
Start date: 2020-12-04, end date: 2020-12-09, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine whether the completed works used in the construction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections from 11032019 case 121120190031 The tasks of this inspection are the prevention, as well as the identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162005291251
Unscheduled inspection
Start date: 2020-12-28, end date: 2021-01-22, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 05102020 case 121120190020 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162005216727
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-11-24, duration: 7
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections from 09102020 case 121120190023the objectives of this audit are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer, of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this audit is to select the necessary compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162005216714
Unscheduled inspection
Start date: 2020-11-16, end date: 2020-11-24, duration: 7
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 09102020 case 121120190022the objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The purpose of this inspection is to select the necessary compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162005238855
Unscheduled inspection
Start date: 2020-11-23, end date: 2020-11-24, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: this check is carried out in order to determine the fact of execution of the instruction from 25092020 1212091101, the term of which expired on 26102020 25092020 1212091102, the term of which expired on 26102020 and drawing up an act based on the results of the inspection, the tasks of this check are the prevention as well as the identification and suppression of violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of a capital construction facility The purpose of this inspection is to select the necessary fulfillment of the requirements of state control bodies supervision of municipal control bodies


# 162005239466
Unscheduled inspection
Start date: 2020-11-26, end date: —, duration:
Authority:
Purpose of inspection:


# 162005196058
Unscheduled inspection
Start date: 2020-10-23, end date: 2020-10-28, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 23052018 case 121120180050 The objectives of this audit are to prevent, identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer with the requirements of mandatory requirements and or requirements established by the municipal legal acts


# 162005196052
Unscheduled inspection
Start date: 2020-10-23, end date: 2020-10-28, duration: 4
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 23052018 case 121120180049 The objectives of this audit are to prevent, identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer with the requirements of mandatory requirements and or requirements established by the municipal legal acts


# 162005196041
Unscheduled inspection
Start date: 2020-10-23, end date: —, duration:
Authority:
Purpose of inspection:


# 162005196030
Unscheduled inspection
Start date: 2020-10-23, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162005147583
Unscheduled inspection
Start date: 2020-10-01, end date: 2020-10-05, duration: 3
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 14032019 case 121120190040 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162005166128
Unscheduled inspection
Start date: 2020-10-07, end date: —, duration:
Authority:
Purpose of inspection:


# 162004474891
Unscheduled inspection
Start date: 2020-08-06, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162004496250
Unscheduled inspection
Start date: 2020-08-24, end date: 2020-08-25, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations design documentation other normative acts norms and rules for determining the fact of execution of the order as well as for the purpose of drawing up an act on the elimination of violations of the execution of the order on the basis of a notice received by the Inspection from 12082020 8455 on the elimination of violations during the construction reconstruction of a capital construction facility that were ordered to be eliminated within the time limit established the order from 30072020 1212067702 to 14082020 and the expiration date of the order from 30072020 1212067702, the deadline for which expired 14082020, The objectives of this audit are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the work performed during the construction of the capital construction facility with the requirements of technical regulations other regulatory legal acts and The subject of this audit is the fulfillment of the requirements of the state control bodies supervision of municipal control bodies


# 162004462755
Unscheduled inspection
Start date: 2020-07-28, end date: —, duration:
Authority:
Purpose of inspection:


# 162004448077
Unscheduled inspection
Start date: 2020-07-08, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162004448076
Unscheduled inspection
Start date: 2020-07-08, end date: 2020-07-09, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order from 21052020 1212043501, the deadline for which has expired 15062020 21052020 1212043502, the deadline for which has expired 15062020 and drawing up an act based on the results of the inspection, the objectives of this inspection are to prevent as well as identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of the facility capital construction works according to the requirements of technical regulations other regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies


# 162004448066
Unscheduled inspection
Start date: 2020-07-08, end date: 2020-07-09, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order from 21052020 1212043402, the term of which expired 15062020 21052020 1212043401, the term of which expired 15062020 and drawing up an act based on the results of the inspection, the objectives of this inspection are to prevent as well as identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of the facility capital construction works according to the requirements of technical regulations other regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies


# 162004448051
Unscheduled inspection
Start date: 2020-07-08, end date: —, duration:
Authority:
Purpose of inspection:


# 162004460414
Unscheduled inspection
Start date: 2020-07-21, end date: 2020-07-22, duration: 2
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order from 22052020 1212044101, the deadline for which expired 13072020 22052020 1212044102, the deadline for which expired 13072020 and drawing up an act based on the results of the inspection, the objectives of this inspection are to prevent as well as identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of the facility capital construction works according to the requirements of technical regulations other regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies


# 162004470060
Unscheduled inspection
Start date: 2020-07-30, end date: —, duration:
Authority:
Purpose of inspection:


# 162004417168
Unscheduled inspection
Start date: 2020-06-03, end date: 2020-06-05, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program of 10122018 case 121120180124 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162004421312
Unscheduled inspection
Start date: 2020-06-01, end date: 2020-06-01, duration: 1
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order from 19032020 1212023701, the deadline for which expired 21052020 and drawing up an act based on the results of the inspection, the objectives of this inspection are to prevent, as well as identify and suppress violations of compliance by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of the compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations and other regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies


# 162004421339
Unscheduled inspection
Start date: 2020-06-01, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162004411041
Unscheduled inspection
Start date: 2020-05-21, end date: 2020-05-22, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the construction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 23.012019 case 121120190005 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162004409594
Unscheduled inspection
Start date: 2020-05-19, end date: 2020-05-19, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order from 11032020 1212020102, the deadline for which has expired 15042020 11032020 1212020101, the deadline for which has expired 15042020 and drawing up an act based on the results of the inspection, the objectives of this inspection are to prevent as well as identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of the facility capital construction works according to the requirements of technical regulations other regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies


# 162004408594
Unscheduled inspection
Start date: 2020-05-15, end date: 2020-05-21, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 05102018 case 121120180106 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162004408592
Unscheduled inspection
Start date: 2020-05-15, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162004408587
Unscheduled inspection
Start date: 2020-05-15, end date: 2020-05-21, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the program of inspections dated 23052018 case 121120180049 The objectives of this audit are to prevent, identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer with the requirements of mandatory requirements and or requirements established by the municipal legal acts


# 162004408584
Unscheduled inspection
Start date: 2020-05-15, end date: 2020-05-21, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 23052018 case 121120180048 The objectives of this inspection are to prevent, identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations other regulatory legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer with the requirements of mandatory requirements and or requirements established by the municipal legal acts


# 162004407789
Unscheduled inspection
Start date: 2020-05-15, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162004380352
Unscheduled inspection
Start date: 2020-04-06, end date: 2020-04-30, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine whether the completed works used in the construction of an object of capital construction of building materials, the results of such work, meet the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 11032019 case 121120190031 The objectives of this inspection are to prevent as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162004380287
Unscheduled inspection
Start date: 2020-04-06, end date: 2020-04-30, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program of 30072018 case 12112014006402 The objectives of this inspection are to prevent, identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of the capital construction facility, the subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162004364480
Unscheduled inspection
Start date: 2020-04-06, end date: —, duration:
Authority:
Purpose of inspection:


# 162004398611
Unscheduled inspection
Start date: 2020-04-21, end date: 2020-04-22, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order from 14022020 1212012002, the deadline for which has expired 13032020 14022020 1212012001, the deadline for which has expired 13032020 and drawing up an act based on the results of the inspection, the objectives of this inspection are to prevent as well as identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of the facility capital construction works according to the requirements of technical regulations other regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies


# 162004333554
Unscheduled inspection
Start date: 2020-03-06, end date: —, duration:
Authority:
Purpose of inspection:


# 162004333537
Unscheduled inspection
Start date: 2020-03-06, end date: 2020-03-11, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This check is carried out in order to determine the compliance of the completed works used in the construction of a capital construction facility with building materials, the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 21.012019 case 121120190008 The objectives of this inspection are to prevent, as well as identify and suppress violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation performed during the construction of a capital construction facility. The subject of this inspection is compliance with mandatory requirements and or requirements established by the municipal legal acts


# 162004325036
Unscheduled inspection
Start date: 2020-03-04, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162004325014
Unscheduled inspection
Start date: 2020-03-04, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 162004325011
Unscheduled inspection
Start date: 2020-03-04, end date: 2020-03-06, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order dated 15012020 1212000702, the deadline for which expired 17022020 15012020 1212000701, the deadline for which expired 17022020 and drawing up an act based on the results of the inspection, the objectives of this inspection are to prevent as well as identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of the facility capital construction works according to the requirements of technical regulations other regulatory legal acts and project documentation The subject of this audit is the fulfillment of the instructions of state control bodies supervision of municipal control bodies


# 162004359676
Unscheduled inspection
Start date: 2020-03-19, end date: —, duration:
Authority:
Purpose of inspection:


# 162004249279
Unscheduled inspection
Start date: 2020-02-03, end date: 2020-02-05, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order dated 09122019 1212135602, the deadline for which expired 20012020 09122019 1212135601, the deadline for which expired 20012020 and drawing up an act based on the results of the inspection, the tasks of this inspection are to prevent as well as identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of a capital construction facility The purpose of this inspection is to comply with the requirements of state control bodies supervision of municipal control bodies


# 162004249342
Unscheduled inspection
Start date: 2020-02-03, end date: 2020-02-05, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the fact of execution of the order from 10122019 1212135702, the term of which expired 20012020 10122019 1212135701, the term of which expired 20012020 and drawing up an act based on the results of the inspection, the tasks of this inspection are to prevent as well as identify and suppress violations of conformity committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer performed during the construction of a capital construction facility The subject of this audit is the fulfillment of the requirements of the state control bodies supervision of municipal control bodies


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.