# 782100414142
Unscheduled inspection
Start date: 2021-07-29, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: g) verification of the completion of the work provided for in the inspection program dated __02 July 2020 in case No. Zh11-02(20)_- installation of internal engineering and technical support networks (June 2021 according to the inspection program No. 03-6547/2020 dated 07/02/2020);
a) compliance with mandatory requirements, including:
compliance of the work performed and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities, which are not subject to energy efficiency requirements) and facility equipment requirements capital construction accounting devices for used energy resources;
# 782100190008
Unscheduled inspection
Start date: 2021-03-22, end date: —, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the completion of the work provided for in the inspection program dated 07/02/2020 (installation of aboveground structures – 02/28/2021) in case No. Zh 11-04(20);
compliance with mandatory requirements, including:
compliance of the work performed and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and equipment requirements of the capital construction facility metering devices for used energy resources;
availability of a building permit;
meeting the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation;
b) compliance with the regulations of the Committee for State Construction Supervision and
State Expertise of the Leningrad Region;
c) holding events:
to prevent harm to life, health of citizens, harm to animals, plants, and the environment;
prevention of natural and man-made emergencies;
to eliminate the consequences of causing such harm.
# 472004474687
Unscheduled inspection
Start date: 2020-08-06, end date: 2020-09-02, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used parts 2 3 and 31 of Article 52 of the Urban Development Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 472004337099
Unscheduled inspection
Start date: 2020-03-04, end date: 2020-04-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471903827361
Unscheduled inspection
Start date: 2019-09-02, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 471902965553
Unscheduled inspection
Start date: 2019-08-14, end date: 2019-09-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of this audit is to verify the fulfillment of the issued instruction on the elimination of identified violations. The subject of this audit is to comply with the instructions of the Committee for State Construction Supervision and State Expertise of the Leningrad Region. The objectives of this audit are to prevent, identify and suppress violations of urban planning legislation by the developer, technical customer, and the person carrying out construction, including technical regulations. And the design objectives of this audit are to prevent, identify and suppress violations of urban planning legislation. by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation, the purpose is to verify the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification. The subject of this audit is compliance with mandatory requirements, including compliance with the work performed and the construction materials used during the construction and reconstruction of the capital construction facility and as well as the results of such work, the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the objectives of this audit are to prevent, identify and suppress violations of the legislation on urban planning committed by the developer, technical customer, or person engaged in construction. including technical regulations and project documentation
# 471902931051
Unscheduled inspection
Start date: 2019-08-05, end date: 2019-08-30, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471902852518
Unscheduled inspection
Start date: 2019-07-04, end date: 2019-07-31, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction
# 471902746689
Unscheduled inspection
Start date: 2019-05-30, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902735994
Unscheduled inspection
Start date: 2019-05-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 781902523069
Unscheduled inspection
Start date: 2019-02-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471801884024
Unscheduled inspection
Start date: 2018-10-01, end date: 2018-10-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 781800625689
Unscheduled inspection
Start date: 2018-08-13, end date: 2018-08-21, duration: —
Authority: Upravlenie po voprosam migracii GU MVD Rossii po gSanktPeterburgu i Leningradskoi oblasti
Purpose of inspection: The audit is carried out in order to verify compliance with the legislation of the Russian Federation in the field of migration. The objectives of this audit are to comply with the requirements of the legislation of the Russian Federation in the field of migration, identify administrative offenses in the field of migration and crimes, bring those responsible for administrative offenses in the field of migration to responsibility, ensure the rights and legitimate interests of foreign citizens and stateless persons, identify and eliminate the causes and conditions conducive to the commission of administrative offenses in the field of migration and crimes
# 471800559876
Unscheduled inspection
Start date: 2018-07-16, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 471800185648
Unscheduled inspection
Start date: 2018-03-05, end date: 2018-04-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the works specified in the notice of the person carrying out the construction on the completion dates of the works that are subject to verification The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility implementation of the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation