Found 7 inspections:

# 111904058600
Unscheduled inspection
Start date: 2019-12-09, end date: 2019-12-20, duration:
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to establish the fulfillment of the previously issued by the Department for Energy Supervision and Supervision of Hydraulic Structures of the Pechora Department of Rostechnadzor of the points of the instruction dated 05092019 250648, the deadline for which expires. The objectives of this audit are to verify the elimination of identified violations specified in the instruction issued by the Department for Energy Supervision and Supervision of Hydraulic Structures of the Pechora Department of Rostechnadzor dated 05092019 250648, the deadline for which is expired The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies


# 111902962221
Unscheduled inspection
Start date: 2019-08-26, end date: 2019-09-06, duration:
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 04072019 261 "On monitoring the preparation of heat supply facilities for operation in the autumn winter period 20192020" issued pursuant to the instructions of Deputy Prime Minister of the Russian Federation Vladimir Mutko dated 19062019 VMP95084THE tasks of this inspection are to verify readiness for the autumn winter period 20192020 and verify compliance with mandatory requirements In the field of energy security, the subject of this audit is to verify compliance with mandatory requirements and or requirements established by municipal legal acts


# 111902841243
Unscheduled inspection
Start date: 2019-07-01, end date: 2019-07-12, duration:
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish the execution of the order dated 25022019 2506801, previously issued by the Department for Energy Supervision and Supervision of Hydraulic Structures of the Pechora Department of Rostechnadzor, the deadline for which has expired Verification of the elimination of identified violations specified in the order dated 25022019 2506801, previously issued by the Department for Energy Supervision and Supervision of Hydraulic Structures of the Pechora Department of Rostechnadzor, the deadline for which has expired The fulfillment of the instructions of the state control and supervision authorities municipal control bodies


# 111902486321
Unscheduled inspection
Start date: 2019-02-11, end date: —, duration:
Authority:
Purpose of inspection:


# 111801761094
Unscheduled inspection
Start date: 2018-09-10, end date: —, duration:
Authority:
Purpose of inspection:


# 11160700715019
Unscheduled inspection
Start date: 2016-09-12, end date: 2016-10-07, duration:
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of the order of the Federal Service for Environmental, Technological and Nuclear Supervision dated 17062016 229 "On monitoring the progress of preparation and assessment of the readiness of electric power and heat supply facilities for operation in the autumn-winter period of 2016-2017" issued pursuant to the instructions of the Deputy Chairman of the Government of the Russian Federation DN Kozak dated 02062016 DKP93275 verification of readiness for the heating period of 2016-2017 verification of mandatory requirements in the field of energy security compliance with mandatory safety requirements in the electric and thermal power industry


# 11150601198673
Unscheduled inspection
Start date: 2015-08-31, end date: 2015-09-25, duration:
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Implementation of Order No. 237 of the Federal Service for Environmental Technological and Nuclear Supervision dated 23062015 On Monitoring the Progress of Preparation and Assessment of the Readiness of Electric Power and Heat Supply Facilities for Operation in the Autumn-winter period 20152016 issued pursuant to the instructions of Deputy Prime Minister of the Russian Federation DN Kozak dated 11062015 DKP93853


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.