# 742101375370
Unscheduled inspection
Start date: 2021-11-26, end date: 2021-12-02, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po ustroistvu naruzhnyh i vnutrennih ograzhdayuschih konstrukcii; montazhu vnutrennih inzhenernyh setei i sistem i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.
# 742101215071
Unscheduled inspection
Start date: 2021-10-22, end date: 2021-10-28, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Sootvetstvie vypolneniya rabot po ustroistvu naruzhnyh i vnutrennih ograzhdayuschih konstrukcii; ustroistvu priyamkov i primenyaemyh stroitelnyh materialov v processe stroitelstva, rekonstrukcii obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15.2 i 15.3 stati 48 nastoyaschego Kodeksa proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3.8 i 3.9 stati 49 nastoyaschego Kodeksa) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami nastoyaschego Kodeksa), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov. 2. Nalichie razresheniya na stroitelstvo. 3. Vypolnenie trebovanii ch.ch. 2,3 i 3.1 st.52 Gradostroitelnogo kodeksa RF.
# 742100586906
Unscheduled inspection
Start date: 2021-09-07, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 742100383404
Unscheduled inspection
Start date: 2021-08-03, end date: 2021-08-09, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the construction of the foundations of the building, the installation of metal structures (in the course of work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities that are not subject to energy efficiency requirements) and the requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.
# 742100277034
Unscheduled inspection
Start date: 2021-06-21, end date: 2021-06-25, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance of the construction of the foundations of the building, the installation of metal structures (in the course of work) and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities that are not subject to energy efficiency requirements) and the requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.
# 742105308160
Unscheduled inspection
Start date: 2021-01-26, end date: 2021-02-01, duration: 5
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1. Compliance with the performance of work according to 1. Performance of PIC work; 2. Excavation; 3. Foundation construction (in the course of work). and the construction materials used during the construction, reconstruction of the capital construction facility, as well as the results of such work, to the requirements of the project documentation approved in accordance with Parts 15, 15.2 and 15.3 of Article 48 of this Code (subject to changes made to the project documentation in accordance with parts 3.8 and 3.9 of Article 49 of this Code) and (or) an information model (if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code), including energy efficiency requirements (with the exception of capital construction facilities to which energy efficiency requirements do not apply) and requirements for equipping the capital construction facility with metering devices for used energy resources. 2. Availability of a building permit. 3. Meeting the requirements of Parts 2.3 and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.
# 741800617667
Unscheduled inspection
Start date: 2018-08-07, end date: 2018-08-28, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po CHelyabinskoi oblasti
Purpose of inspection: 1 provedenie proverki i analiza svedenii soderzhaschiesya v predstavlennyh soiskatelem licenzii licenziatom zayavleniyah i dokumentah v celyah ocenki sootvetstviya takih svedenii polozheniyam chastei 1 i 3 stati 13 i chasti 3 stati 18 Federalnogo zakona ot 04052011 99FZ a takzhe svedeniyam o soiskatele licenzii ili licenziate soderzhaschimsya v edinom gosudarstvennom reestre yuridicheskih lic edinom gosudarstvennom reestre individualnyh predprinimatelei i drugih federalnyh informacionnyh resursah 2 proverka sostoyaniya tehnicheskih sredstv sredstv izmereniya oborudovaniya inyh obektov kotorye predpolagaetsya ispolzovat soiskatelem licenzii ili licenziatom pri osuschestvlenii licenziruemogo vida deyatelnosti v celyah ocenki sootvetstviya takih obektov 3 proverka dokumentov podtverzhdayuschih nalichie neobhodimyh dlya osuschestvleniya licenziruemogo vida deyatelnosti rabotnikov v celyah ocenki sootvetstviya rabotnikov licenzionnym trebovaniyam