Found 100 inspections:

# 772100166066
Unscheduled inspection
Start date: 2021-05-05, end date: 2021-05-14, duration: 7
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya predpisaniya ot 30 yanvarya 2020 g. № 49-G/3.3-20/H-107. Zadachami nastoyaschei proverki yavlyayutsya: osuschestvlenie kontrolya za prinyatymi yuridicheskim licom merami po ispolneniyu predpisaniya i soblyudeniyu obyazatelnyh trebovanii zakonodatelstva o gradostroitelnoi deyatelnosti pri stroitelstve, rekonstrukcii obekta kapitalnogo stroitelstva; prinyatie mer po ustraneniyu narushenii obyazatelnyh trebovanii (v sluchae ih vyyavleniya) i po privlecheniyu k otvetstvennosti lic, dopustivshih narusheniya trebovanii Federalnyh zakonov i inyh normativnyh pravovyh aktov. Predmetom proverki yavlyaetsya vypolnenie predpisaniya organa gosudarstvennogo kontrolya (nadzora)


# 772100100833
Unscheduled inspection
Start date: 2021-04-05, end date: 2021-04-07, duration: 3
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya predpisaniya ot 28 yanvarya 2021 g. № 12-G/3.3-20/H-107. Zadachami nastoyaschei proverki yavlyayutsya: osuschestvlenie kontrolya za prinyatymi yuridicheskim licom merami po ispolneniyu predpisaniya i soblyudeniyu obyazatelnyh trebovanii zakonodatelstva o gradostroitelnoi deyatelnosti pri stroitelstve, rekonstrukcii obekta kapitalnogo stroitelstva; prinyatie mer po ustraneniyu narushenii obyazatelnyh trebovanii (v sluchae ih vyyavleniya) i po privlecheniyu k otvetstvennosti lic, dopustivshih narusheniya trebovanii Federalnyh zakonov i inyh normativnyh pravovyh aktov. Predmetom proverki yavlyaetsya vypolnenie predpisaniya organa gosudarstvennogo kontrolya (nadzora)


# 772004474360
Unscheduled inspection
Start date: 2020-08-28, end date: —, duration:
Authority:
Purpose of inspection:


# 772004447659
Unscheduled inspection
Start date: 2020-07-10, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772004428693
Unscheduled inspection
Start date: 2020-06-08, end date: 2020-06-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 772004428688
Unscheduled inspection
Start date: 2020-06-08, end date: 2020-06-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 772004417448
Unscheduled inspection
Start date: 2020-05-27, end date: 2020-06-17, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, the subject of verification is the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code compliance with the performance of works and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such works with the requirements of design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used


# 772004341168
Unscheduled inspection
Start date: 2020-03-11, end date: 2020-03-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 772004303524
Unscheduled inspection
Start date: 2020-02-25, end date: 2020-03-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 772004265521
Unscheduled inspection
Start date: 2020-02-10, end date: —, duration:
Authority:
Purpose of inspection:


# 772004265535
Unscheduled inspection
Start date: 2020-02-10, end date: —, duration:
Authority:
Purpose of inspection:


# 772004225081
Unscheduled inspection
Start date: 2020-02-10, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 772004209523
Unscheduled inspection
Start date: 2020-01-21, end date: 2020-02-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771904058287
Unscheduled inspection
Start date: 2019-12-03, end date: 2019-12-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771904139430
Unscheduled inspection
Start date: 2019-12-23, end date: 2019-12-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer's task of verification, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check and verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771904065417
Unscheduled inspection
Start date: 2019-12-06, end date: 2019-12-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, the subject of verification is the fulfillment by the person carrying out the construction of the requirements of part 3 of Article 52 of the Urban Planning Code, compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation in accordance with the requirements of the technical regulations of the project documentation in accordance with the requirements of the technical regulations of the project documentation in accordance with the requirements of the technical regulations of the project documentation in accordance with the requirements of the technical regulations of the project documentation in accordance with the requirements of the technical regulations of the project documentation in accordance with the requirements of the technical regulations of the project documentation in accordance with the requirements of the including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used


# 771904099093
Unscheduled inspection
Start date: 2019-12-12, end date: 2019-12-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify compliance with the instructions of the Moscow State Construction Supervision


# 771904105513
Unscheduled inspection
Start date: 2019-12-16, end date: —, duration:
Authority:
Purpose of inspection:


# 771904020003
Unscheduled inspection
Start date: 2019-11-27, end date: 2019-11-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903940573
Unscheduled inspection
Start date: 2019-11-08, end date: —, duration:
Authority:
Purpose of inspection:


# 771903942776
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the verification of compliance with the requirements of the task of the audit, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to verify the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903890584
Unscheduled inspection
Start date: 2019-10-25, end date: —, duration:
Authority:
Purpose of inspection:


# 771903809492
Unscheduled inspection
Start date: 2019-10-03, end date: 2019-10-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903914532
Unscheduled inspection
Start date: 2019-10-30, end date: 2019-11-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771903595186
Unscheduled inspection
Start date: 2019-09-11, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 771903561871
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-10-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with checking the fulfillment of the prescriptionthe tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development activity by the audited person. The purpose of the audit is to verify the elimination of violations specified in the prescription issued by Mosgosstroynadzor


# 771903632110
Unscheduled inspection
Start date: 2019-09-09, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803492932
Unscheduled inspection
Start date: 2019-09-09, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803471833
Unscheduled inspection
Start date: 2019-08-02, end date: 2019-08-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803464848
Unscheduled inspection
Start date: 2019-07-22, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803451298
Unscheduled inspection
Start date: 2019-07-05, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803451100
Unscheduled inspection
Start date: 2019-07-05, end date: 2019-07-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor, compliance of the work and construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77190803434473
Unscheduled inspection
Start date: 2019-06-10, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803435601
Unscheduled inspection
Start date: 2019-06-12, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77190803443568
Unscheduled inspection
Start date: 2019-06-21, end date: 2019-07-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu provedenie meropriyatii po kontrolyu v svyazi s vypolneniem programmy proverok na osnovanii utverzhdennoi programmy proverok ot 02112018 1Zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii trebovanii proektnoi dokumentacii zakonodatelstva o gradostroitelnoi deyatelnostiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov


# 77190803413192
Unscheduled inspection
Start date: 2019-05-14, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77190803412063
Unscheduled inspection
Start date: 2019-05-14, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803415480
Unscheduled inspection
Start date: 2019-05-15, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803422309
Unscheduled inspection
Start date: 2019-05-22, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803403626
Unscheduled inspection
Start date: 2019-04-24, end date: 2019-05-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803360099
Unscheduled inspection
Start date: 2019-03-01, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803357730
Unscheduled inspection
Start date: 2019-03-04, end date: 2019-03-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77190803328728
Unscheduled inspection
Start date: 2019-02-11, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803338275
Unscheduled inspection
Start date: 2019-02-15, end date: 2019-02-27, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu sootvetstvie obekta kapitalnogo stroitelstva trebovaniyam tehnicheskih reglamentov i proektnoi dokumentacii na osnovanii utverzhdennoi programmy proverok ot 02112018 1Zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov


# 77190803341376
Unscheduled inspection
Start date: 2019-02-22, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803329231
Unscheduled inspection
Start date: 2019-02-07, end date: —, duration:
Authority:
Purpose of inspection:


# 77190803314769
Unscheduled inspection
Start date: 2019-01-16, end date: 2019-02-08, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803309279
Unscheduled inspection
Start date: 2018-12-26, end date: 2019-01-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803308915
Unscheduled inspection
Start date: 2018-12-29, end date: 2019-01-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803302084
Unscheduled inspection
Start date: 2018-12-18, end date: 2018-12-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803282357
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-12-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803282356
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-12-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803269930
Unscheduled inspection
Start date: 2018-11-06, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803285459
Unscheduled inspection
Start date: 2018-11-29, end date: 2018-12-12, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803263086
Unscheduled inspection
Start date: 2018-10-25, end date: 2018-11-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803250409
Unscheduled inspection
Start date: 2018-10-11, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803221461
Unscheduled inspection
Start date: 2018-09-06, end date: 2018-10-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803220968
Unscheduled inspection
Start date: 2018-09-06, end date: 2018-10-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803200692
Unscheduled inspection
Start date: 2018-08-14, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803216982
Unscheduled inspection
Start date: 2018-08-31, end date: 2018-09-27, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803214850
Unscheduled inspection
Start date: 2018-08-29, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803183548
Unscheduled inspection
Start date: 2018-07-18, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803187942
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803158505
Unscheduled inspection
Start date: 2018-06-13, end date: 2018-06-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 771800462596
Unscheduled inspection
Start date: 2018-06-07, end date: 2018-07-05, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: proverka provoditsya s celyu federalnogo gosudarstvennogo nadzora za soblyudeniem trebovanii trudovogo zakonodatelstva i inyh normativnyh pravovyh aktov soderzhaschih normy trudovogo prava na osnovanii motivirovannogo predstavleniya ot 05062018 g gosudarstvennogo inspektora truda Gosudarstvennoi inspekcii truda v gorode Moskve SP YAgodinca


# 77180803165309
Unscheduled inspection
Start date: 2018-06-21, end date: 2018-06-25, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803151568
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-29, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803141447
Unscheduled inspection
Start date: 2018-05-17, end date: 2018-05-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803143654
Unscheduled inspection
Start date: 2018-05-03, end date: 2018-05-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803113683
Unscheduled inspection
Start date: 2018-04-03, end date: 2018-04-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803114884
Unscheduled inspection
Start date: 2018-03-30, end date: 2018-04-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803097577
Unscheduled inspection
Start date: 2018-03-12, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77180803099588
Unscheduled inspection
Start date: 2018-03-13, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803075939
Unscheduled inspection
Start date: 2018-03-14, end date: 2018-04-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803087502
Unscheduled inspection
Start date: 2018-02-12, end date: —, duration:
Authority:
Purpose of inspection:


# 77180803076334
Unscheduled inspection
Start date: 2018-02-02, end date: 2018-02-08, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803079744
Unscheduled inspection
Start date: 2018-01-31, end date: 2018-02-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803074154
Unscheduled inspection
Start date: 2018-01-31, end date: 2018-02-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77180803079460
Unscheduled inspection
Start date: 2018-01-19, end date: 2018-02-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77180803066060
Unscheduled inspection
Start date: 2018-01-19, end date: 2018-02-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170803034884
Unscheduled inspection
Start date: 2017-12-26, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802819215
Unscheduled inspection
Start date: 2017-11-08, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802905479
Unscheduled inspection
Start date: 2017-11-30, end date: 2017-12-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802764672
Unscheduled inspection
Start date: 2017-10-19, end date: 2017-10-24, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802708318
Unscheduled inspection
Start date: 2017-10-10, end date: 2017-10-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170802175968
Unscheduled inspection
Start date: 2017-09-07, end date: 2017-09-07, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802253283
Unscheduled inspection
Start date: 2017-09-08, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802041300
Unscheduled inspection
Start date: 2017-09-06, end date: 2017-09-11, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701903695
Unscheduled inspection
Start date: 2017-08-15, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701894277
Unscheduled inspection
Start date: 2017-08-16, end date: 2017-08-31, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701889713
Unscheduled inspection
Start date: 2017-08-10, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701869592
Unscheduled inspection
Start date: 2017-08-09, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77170701863371
Unscheduled inspection
Start date: 2017-08-03, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77170701848870
Unscheduled inspection
Start date: 2017-07-28, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701832354
Unscheduled inspection
Start date: 2017-07-28, end date: 2017-08-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701726339
Unscheduled inspection
Start date: 2017-06-19, end date: 2017-06-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701719365
Unscheduled inspection
Start date: 2017-06-19, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701694009
Unscheduled inspection
Start date: 2017-06-14, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701686544
Unscheduled inspection
Start date: 2017-06-08, end date: 2017-06-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701649417
Unscheduled inspection
Start date: 2017-05-29, end date: —, duration:
Authority:
Purpose of inspection:


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.